001 Hak Akses (open/membership)membership
700 Entri Tambahan Nama OrangAyomi Dita Rarasati, supervisor; Mohammad Ihsan, supervisor; Henki Wibowo Ashadi, examiner; Rosmariani Ariffudin, examiner; Afrizal Nursin, examiner
336 Content Typetext (rdacontent)
264b Nama PenerbitFakultas Teknik Universitas Indonesia
710 Entri Tambahan Badan KorporasiUniversitas Indonesia. Fakultas Teknik
049 No. Barkod15-25-24892467
504 Catatan Bibliografipages 91-94
852 LokasiPerpustakaan UI
338 Carrier Typeonline resource (rdacarrier)
590 Cat. Sumber Pengadaan KoleksiDeposit;Deposit
903 Stock Opname
534 Catatan Versi Asli
Tahun Buka Akses2021
053 No. Induk15-25-24892467
653 Kata Kunciproblem factors for interface management; interface management; time performance; existing oil and gas field optimization project; natuna block
040 Sumber PengataloganLibUI ind rda
245 Judul UtamaStrategi Pengembangan Interface Management Untuk Meningkatkan Kinerja Waktu Pada Proyek Modifikasi Fasilitas Produksi Migas Eksisting Oleh PT. XYZ Di Blok Natuna = Interface Management Development Strategy To Improve Time Performance In Modification Of Existing Oil And Gas Production Facilities Project By PT. XYZ At Natuna Block
264c Tahun Terbit2021
650 Subyek TopikInterface management
850 Lembaga PemilikUniversitas Indonesia
520 Ringkasan/Abstrak/IntisariDalam industri migas di Indonesia, sudah tercatat dalam kurun waktu dua tahun terakhir, 8 proyek pengembangan lapangan migas eksisting mundur dari jadwal onstream yang sudah ditentukan. Fenomena ini perlu mendapatkan perhatian khusus. Mundurnya jadwal onstream dari proyek-proyek tersebut karena kurangnya koordinasi antar pihak yang terkait seperti keterlambatan rig, masalah administrasi, belum adanya buyer, keterlambatan material dan lain-lain. Manajemen interface merupakan salah satu upaya untuk mengatasi masalah kurangnya koordinasi antar pihak mengingat proyek-proyek di industri migas merupakan mega proyek yang melibatkan banyak pihak. Tujuan dari penelitian ini untuk mengembangkan strategi manajemen interface dengan mengidentifikasi masalah interface yang berkaitan dengan kinerja waktu dan mencari masalah interface mana yang sangat mempengaruhi kinerja waktu pada proyek pengembangan lapangan migas eksisting pada Blok Natuna. Penelitian ini dibagi menjadi 4 tahapan, dimana tahap pertama adalah analisa arsip dan dilanjutkan dengan validasi pakar, tahap ketiga adalah adalah pilot survey & kuisioner responden, dan yang terakhir adalah interview langsung untuk mengetahui strategi pengembangan manajemen interface untuk meningkatkan kinerja waktu. Terdapat 38 masalah interface dengan 9 kategori faktor, yaitu; partisipan, metode/proses, praktek, sumber daya, manajemen, informasi, lingkungan, hukum serta regulasi dan bid serta kontrak. Faktor analisis dilakukan setelah validasi pakar, lalu dilakukan uji validitas dan uji realibilitas dengan bantuan software SPSS. Hasil analisis data akan digunakan untuk membuat strategi dalam pengembangan manajemen interface pada proyek modifikasi lapangan migas eksisting di Blok Natuna. ......In the oil and gas industry in Indonesia, it has been recorded that in the last two years, 8 existing oil and gas field development projects have been delayed from the onstream schedule that has been determined. This phenomenon needs special attention. The delay in the onstream schedule of these projects is due to lack of coordination between related parties such as rig delays, administrative problems, the absence of buyers, material delays and others. Interface management is one of the efforts to overcome the problem of lack of coordination between parties considering that projects in the oil and gas industry are mega projects that involve many parties. The purpose of this study is to develop an interface management strategy by identifying interface problems related to time performance and finding out which interface problems greatly affect time performance in the existing oil and gas field development project in the Natuna Block. This research is divided into 4 stages, where the first stage is archive analysis and continued with expert validation, the third stage is pilot survey & respondent questionnaire, and the last is direct interview to find out the interface management development strategy to improve time performance. There are 38 interface problems with 9 categories of factors, namely; participants, methods/processes, practices, resources, management, information, environment, laws and regulations and bids and contracts. Factor analysis is carried out after expert validation, then validity and reliability tests are carried out with the help of SPSS software. The results of the data analysis will be used to create strategies in the development of interface management in the modification project of the existing oil and gas field in the Natuna Block.
904b Pemeriksa Lembar KerjaAmiarsih Indah Purwiati-Juli 2025
090 No. Panggil SetempatT-pdf
d-Entri Utama Nama Orang
500 Catatan UmumDapat diakses di UIANA (lib.ui.ac.id) saja.
337 Media Typecomputer (rdamedia)
d-Entri Tambahan Nama Orang
526 Catatan Informasi Program StudiTeknik Sipil
100 Entri Utama Nama OrangMuhammad Darussalam, author
264a Kota TerbitDepok
300 Deskripsi Fisikxvii, 94 pages : illustration + appendix
904a Pengisi Lembar KerjaAmiarsih Indah Purwiati-Juli 2025
Akses Naskah Ringkas
856 Akses dan Lokasi Elektronik
502 Catatan Jenis KaryaTesis
041 Kode Bahasaind