Tinjauan optimalisasi biaya dan waktu menggunakan metode least cost scheduling. Studi kasus: proyek fly over Arif Rahman Hakim, Depok = Optimalization study of cost and duration with least cost scheduling method. Case study: Arif Rahman Hakim's Flyover project, Depok

Tri Budiarso; Firdaus Ali, supervisor (Fakultas Teknik Universitas Indonesia, 2008)

 Abstrak

Dalam pelaksanaan proses konstruksi, percepatan waktu penyelesaian proyek dari rencana awal sering ditemui untuk mengembalikan ke kondisi yang normal akibat keterlambatan atau membuat kondisi yang lebih baik untuk mempercepat penyelesaian proyek konstruksi tersebut. Metode least- cost scheduling merupakan cara yang sering digunakan dalam mengoptimalisasikan biaya dan penjadwalan dari sebuah proyek konstruksi.
Metode least-cost scheduling menurut Brian J Dregar(1992) pada dasarnya mengkaji hubungan antara waktu selesainya suatu bagian pekerjaan dengan biaya proyek yang bertujuan meyakinkan klien, meningkatkan cara pencapaian mutu, mencapai batas waktu yang telah ditentukan, mengendalikan pengeluaran biaya, dan mengembangkan minimum-cost schedule sesuai dengan permintaan klien dan komitmen proyek.
Namun menurut Stevens (1990), solusi least cost tidak dapat dibuktikan secara absolut karena durasi aktivitas maupun biaya tidak dapat diketahui secara pasti diawal. Diguakan pendekatan probalistik setelah tahapan deterministik dengan metode least-cost scheduling. Setelah melakukan pendekatan studi kasus pada Proyek Pembangunan Flyover Arif Rahman Hakim, Depok, yang mewakili kondisi diperlukannya percepatan, didapat biaya optimum sebesar Rp. Rp. 1,725,811,984.00 pada durasi normal pelaksanaan yaitu 67 hari.

During planning and execution of construction project, it often becomes necessary to escalate the duration of the project in order to adjust to the original schedule, due to time overrun or to simply finished the project ahead of schedule. A widely use technique for reducing the duration of a project in term of project schedule and cost optimalization is commonly referred to a least-cost scheduling.
According to Brian J Dregar (1992), least-cost scheduling method, basically is to examine relation between finishing time from certain activity duration with project cost to assure owner, increased the project quality, finished the project according to time schedule, control the cost project, and to gain minimum-cost schedule according to the owner?s demand and project goal.
But, According to Stevens (1990), there is no absolute, provable least-cost solution, because the activity durations and cost values cannot be precisely known in the beginning. The probabilistic approach were used after deterministic with least-cost scheduling technique.
After case study approach at Arif Rahman Hakim?s Flyover project, Depok, which represent the condition that need to be shorten, the result the optimum cost Rp. 1,715,811,984.00 in normal duration that is 67 days.

 Metadata

Jenis Koleksi : UI - Skripsi Open
No. Panggil : S35753
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2008
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xviii, 84 pages. : illustration ; 30 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S35753 14-17-562488751 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 123077
Cover