UI - Tesis Open :: Kembali

UI - Tesis Open :: Kembali

Faktor penyebab terjadinya klam yang mempengaruhi kinerja waktu proyek konstruksi jalan tol di Jabodetabek

Pasaribu, Andreas Partogi ; Heddy Rohandi Agah, supervisor; Ayomi Dita Rarasati, supervisor; Krishna Mochtar, supervisor; Setyo Suprijadi, examiner ([Publisher not identified] , 2009)

 Abstrak

ABSTRAK
Proyek konstruksi semakin hari menjadi semakin kompleks sehubungan dengan standar-standar baru yang ditetapkan, teknologi yang canggih, dan keinginan pemilik proyek untuk melakukan penambahan ataupun perubahan lingkup pekerjaan. Suksesnya sebuah proyek tak lepas dari kerja sama antara pihak-pihak yang terlibat didalamnya yaitu pemilik proyek dan kontraktor. Pihakpihak tersebut mempunyai kepentingan dan tujuan yang berbeda sehingga konflik/perselisihan selalu timbul akibat perbedaan pendapat pada saat perencanaan dan pembangunan proyek dan menimbulkan klaim. Khusus untuk pembangunan jalan tol di Indonesia, hampir keseluruhan proyek pembangunan jalan tol di Indonesia terlambat dari jadwal yang ditetapkan. Penelitian dilakukan dengan mengadakan survei dengan menggunakan kuisioner, dan hasilnya akan diolah dengan analisa statistik deskriptif dan korelasi dengan menggunakan program SPSS.
Hasil yang didapatkan dari penelitian ini bahwa terdapat 15 (lima belas) faktor penyebab terjadinya klaim: keterlambatan dalam persetujuan desain/gambar (working drawing), kekurangan atau ketidaklengkapan dalam gambar desain, keterlambatan penyerahan lahan, keterlambatan menyetujui detail jadwal yang diajukan kontraktor, perintah untuk menunda suatu pekerjaan karena alasan pendanaan, keterlambatan pengiriman material, pembayaran termin yang terlambat (tidak tepat waktu), kesalahan perhitungan perencanaan, perubahan metode pelaksanaan pekerjaan, perubahan mutu material/bahan, perubahan desain, spesifikasi pelaksanaan yang tidak sempurna/tidak jelas, perbedaan kondisi bawah tanah (terdapat utilitas seperti pipa GAS, PDAM dan kabel PLN), kenaikan nilai tukar rupiah dan inflasi, dan banjir, angin ribut, kerusuhan, demontrasi atau keadaan huru-hara. Dari 15 faktor penyebab klaim, terdapat 2 (dua) faktor dominan penyebab terjadinya klaim dan mempengaruhi kinerja waktu proyek konstruksi jalan tol adalah keterlambatan pembayaran termin dan perubahan desain.

ABSTRACT
Nowdays, Construction projects become increasingly more complex in connection with the new standards are set, advanced technology, and the desires of the owner to make additions or changes in scope of work. The success of a project could not be separated from the cooperation between the parties involved such as the project owners and contractors. The parties have a interest and different purpose so that the conflicts/disputes always arise due to differences of opinion at the time of planning and development projects and lead to claims. Especially for the construction of toll roads in Indonesia, almost all highway construction projects in Indonesia miss the fixed scheduled. Research carried out by conducting a survey using questionnaires, and the results is process using descriptive statistical analysis and correlation using SPSS program.
The results of this study that there are 15 (fifteen) factors causing claim: delay in designs/drawings approval (working drawings), deficiencies or omissions in the design drawings, delay in delivery of land, delay in agreeing details of the contractor?s schedule, the order to suspend a job for reasons funding, delay in material delivery, late payment terms, the calculation error of planning, change methods of work, change the quality of materials, change the design, implementation specifications that are not perfect/not clear, differences in underground conditions, increase in the exchange rate and inflation, and floods, hurricanes, riots, demonstrations or riots circumstances. From 15 factors that cause the claim, 2 (two) dominant factors causing claim and affect the time performance of toll road construction project are late payment terms and change in design.

 Metadata

Jenis Koleksi : UI - Tesis Open
No. Panggil : T26715
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Penerbitan : [Place of publication not identified]: [Publisher not identified], 2009
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xii, 107 pages : illustration ; 30 cm. + Appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T26715 15-19-819736507 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 128693
Cover