Optimalisasi pengoperasian pembangkit listrik di pengolahan minyak dan gas bumi dengan analisa keandalan : studi kasus Grissik Central Gas Plant = Power generation optimization in gas plant using reliability analysis : case in Grissik Central Gas Plant / Jufri Mantianto

Jufri Mantianto; Rinaldy Dalimi, supervisor; Rudy Setiabudy, examiner; Iwa Garniwa M.K., examiner ([Publisher not identified] , 2013)

 Abstrak


Pada sistem tenaga listrik, akan selalu timbul konflik antara tingkat
keandalan dengan biaya, baik itu dalam tahap perencanaan maupun tahap operasi,
sehingga perlu dicari titik optimum antara biaya yang dikeluarkan dengan tingkat
keandalan yang dapat diterima. Terkait dengan hal ini akan dibahas mengenai
optimalisasi pengoperasian pembangkit di pengolahan minyak dan gas bumi
Grissik Central Gas Plant dengan analisa tingkat keandalan, yang akan
membandingkan antara penghematan biaya yang diperoleh dengan kerugian yang
ditimbulkan akibat keandalan sistem pembangkit yang berkurang. Load shedding
akan diterapkan pada sistem tenaga listrik untuk mengurangi kerugian yang
timbul, selain itu juga dari sisi operasional akan dikaji kemampuan pembangkit
pada saat start motor besar. Berdasarkan hasil perhitungan dan analisa,
optimalisasi pengoperasian pembangkit di Grissik Central Gas Plant dapat
diterima secara teknis, dan akan memberikan peluang penghematan sebesar USD
391.687,00 per tahun.

ABSTRACT
In power system, the economic and reliability constraint can conflict, both in
design or operational stage, then need to optimize cost with acceptable system
reliability. According to the above statement, will be discussed power generation
optimization in Grissik Central Gas Plant using reliability analysis. It will
compare between saving cost opportunity and interruption value because of
reduce system reliability. Load shedding system will be implemented in the power
system to minimize the loss. Beside that from the operational point of view, will be
analyzed power generation ability during big motor starting. Based on
calculation and analysis, power generation optimization in Grissik Central Gas
Plant technically accepted and can give saving opportunity around USD
391.687,00 per year.

 File Digital: 1

Shelf
 T35294-Jufri Mantianto.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T35294
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : [Place of publication not identified]: [Publisher not identified], 2013
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xiii, 56 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T35294 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20348844
Cover