Penentuan waktu untuk membangun pembangkit listrik tenaga sampah berbasis sampah padat rumah tangga dan sampah padat industri kelapa sawit = The determination of time to build waste power plant based municipal solid waste and industrial palm solid waste / Indah Prihastuti

Indah Prihastuti; Farizal, supervisor; Lubis, Achjar Yusuf, supervisor; Isti Surjandari Prajitno, co-promotor; Rahmat Nurcahyo, examiner (Fakultas Teknik Universitas Indonesia, 2013)

 Abstrak

ABSTRAK
Pembangkit Listrik Tenaga Sampah (PLTSa) merupakan pembangkit listrik yang
ramah lingkungan yang dapat mengatasi masalah tingginya pertumbuhan sampah
di Indonesia sekaligus memenuhi kebutuhan listrik untuk masyarakat.
Berdasarkan grafik dari kedua model estimasi produksi metana, produksi gas
metana dan laju penurunannya berbeda untuk setiap komposisi dan jenis sampah.
Produksi gas metana menentukan banyaknya listrik yang dihasilkan yang pada
akhirnya mempengaruhi besarnya pendapatan. Oleh karena itu, penentuan waktu
untuk membangun PLTSa menjadi faktor penting untuk diperhatikan karena dapat
mempengaruhi layak atau tidaknya investasi. Penelitian ini menggunakan sampah
padat rumah tangga dan sampah padat industri kelapa sawit yang dibedakan
menjadi 5 skenario komposisi sebagai bahan baku untuk PLTSa dan
menggunakan dua model estimasi produksi metana, yaitu model US EPA dan
model EPER France. Analisis kelayakan investasi yang dilakukan menggunakan
metode NPV, IRR, dan Payback Period. Setelah dilakukan simulasi pembangunan
PLTSa dengan adanya penundaan waktu dalam membangun, maka untuk skenario
1,4, dan 5, waktu untuk membangun PLTSa yang masih layak dan memberikan
keuntungan adalah dalam range tahun pembangunan awal 2014-2015, sedangkan
untuk skenario 2 dan 3 dalam range tahun pembangunan awal 2014-2018 dimana
pada tahun tersebut NPV masih bernilai positif. Sedangkan nilai NPV tertinggi
untuk semua skenario adalah pada tahun 2014 atau tahun tercepat PLTSa dapat
dibangun.
ABSTRACT
Waste Power Plant (PLTSa) is an environmentally friendly power plant that can
overcome the problem of waste growth in Indonesia as well as meet the electricity
needs for the residents. Based on the graphs from the two models for estimating
methane generation, methane generation and the rate of decline is different for
each composition and type of waste. Methane generation determine the amount of
electricity that is generated which eventually affects the income. Therefore, the
determination of time to build PLTSa is an important factor to consider because it
can affect the feasibility of investment. This study uses municipal solid waste and
industrial palm solid waste which is divided into 5 composition scenarios as
feedstock for PLTSa and uses two models for estimating methane generation, the
U.S. EPA and EPER France model. Investment feasibility analysis is performed
using the method of NPV, IRR, and Payback Period. After doing the simulation of
construction PLTSa with a delay time in build, then for scenario 1, 4, and 5, a
time to build PLTSa which still feasible and provide profit is in the range of early
construction years from 2014 to 2015, while for scenario 2 and 3 in range of early
construction years from 2014 to 2018 where the NPV is still positive in that year.
And the highest NPV value for all scenarios is in 2014 or the fastest year PLTSa
can be built.

 File Digital: 1

Shelf
 T36076-Indah Prihastuti.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T36076
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : [Place of publication not identified]: Fakultas Teknik Universitas Indonesia, 2013
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xvi, 109 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T36076 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20350511
Cover