Aplikasi penjadwalan linear scheduling dengan pendekatan metode singularity function pada proyek pembangunan breakwater di Pelabuhan Kalibaru = Application of linear scheduling with singularity function method at breakwater project development in port of Kalibaru / Andi Muhammad Adam

Andi Muhammad Adam; Yusuf Latief, supervisor; Rully Andhika, supervisor; Setyo Suprijadi, examiner; Petroceany, Jade Sjafrecia, examiner (Fakultas Teknik Universitas Indonesia, 2014)

 Abstract

ABSTRAK
Breakwater merupakan proyek linear construction projects dengan tipe pekerjaan
berulang (repetitive work activities), namun di Indonesia penjadwalan untuk
pekerjaan repetitive project masih menggunakan penjadwalan konvensional,
khususnya pada proyek breakwater pelabuhan Kalibaru Jakarta. Metode linear
scheduling dengan singularity function diaplikasikan pada pembangunan
breakwater Pelabuhan Kalibaru mengingat metode tersebut mempunyai banyak
kelebihan. Dalam penelitian ini dilakukan analisa terhadap jadwal pelaksanaan
rencana yang memiliki durasi pekerjaan yaitu 485 hari serta terhadap nilai buffer
antar kegiatan. Hasil analisa dengan singularity function menyimpulkan dengan
mengoptimalkan nilai buffer antar kegiatan dapat mengurangi durasi pekerjaan.
Hasil optimal yang didapat adalah durasi pekerjaan 274 hari.

ABSTRACT
Breakwater is a linear construction project with repetitive work activities, but in
Indonesia scheduling for repetitive projects are still using conventional
scheduling, especially in the construction of breakwater project in Kalibaru
Jakarta. Linear scheduling method with singularity function is applied in the
construction of breakwater at the Port of Kalibaru considering the method has
many advantages. In this research, an analysis of the plan implementation
schedule which has duration of 485 days, and an analysis to the value of the buffer
between activities. The results of the singularity function analysis conclude by
optimizing the value of buffers between activities can reduce the duration of the
work. Optimal results are obtained work duration is 274 days.

 Digital Files: 1

Shelf
 S56325-Andi Muhammad Adam.pdf :: Download

LOGIN required

 Metadata

Collection Type : UI - Skripsi Membership
Call Number : S56325
Main entry-Personal name :
Additional entry-Personal name :
Study Program :
Subject :
Publishing : [Place of publication not identified]: Fakultas Teknik Universitas Indonesia, 2014
Cataloguing Source LibUI ind rda
Content Type text
Media Type unmediated ; computer
Carrier Type volume ; online resource
Physical Description xiv, 96 pages : illustration ; 30 cm + appendix
Concise Text
Holding Institution Universitas Indonesia
Location Perpustakaan UI, Lantai 3
  • Availability
  • Review
  • Cover
Call Number Barcode Number Availability
S56325 TERSEDIA
Review:
No review available for this collection: 20388344
Cover