UI - Skripsi Membership :: Kembali

UI - Skripsi Membership :: Kembali

Aplikasi penjadwalan linear scheduling dengan pendekatan metode singularity function pada proyek pembangunan breakwater di Pelabuhan Kalibaru = Application of linear scheduling with singularity function method at breakwater project development in port of Kalibaru / Andi Muhammad Adam

Andi Muhammad Adam; Yusuf Latief, supervisor; Rully Andhika, supervisor; Setyo Suprijadi, examiner; Petroceany, Jade Sjafrecia, examiner (Fakultas Teknik Universitas Indonesia, 2014)

 Abstrak

ABSTRAK
Breakwater merupakan proyek linear construction projects dengan tipe pekerjaan
berulang (repetitive work activities), namun di Indonesia penjadwalan untuk
pekerjaan repetitive project masih menggunakan penjadwalan konvensional,
khususnya pada proyek breakwater pelabuhan Kalibaru Jakarta. Metode linear
scheduling dengan singularity function diaplikasikan pada pembangunan
breakwater Pelabuhan Kalibaru mengingat metode tersebut mempunyai banyak
kelebihan. Dalam penelitian ini dilakukan analisa terhadap jadwal pelaksanaan
rencana yang memiliki durasi pekerjaan yaitu 485 hari serta terhadap nilai buffer
antar kegiatan. Hasil analisa dengan singularity function menyimpulkan dengan
mengoptimalkan nilai buffer antar kegiatan dapat mengurangi durasi pekerjaan.
Hasil optimal yang didapat adalah durasi pekerjaan 274 hari.

ABSTRACT
Breakwater is a linear construction project with repetitive work activities, but in
Indonesia scheduling for repetitive projects are still using conventional
scheduling, especially in the construction of breakwater project in Kalibaru
Jakarta. Linear scheduling method with singularity function is applied in the
construction of breakwater at the Port of Kalibaru considering the method has
many advantages. In this research, an analysis of the plan implementation
schedule which has duration of 485 days, and an analysis to the value of the buffer
between activities. The results of the singularity function analysis conclude by
optimizing the value of buffers between activities can reduce the duration of the
work. Optimal results are obtained work duration is 274 days.

 File Digital: 1

Shelf
 S56325-Andi Muhammad Adam.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S56325
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : [Place of publication not identified]: Fakultas Teknik Universitas Indonesia, 2014
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xiv, 96 pages : illustration ; 30 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S56325 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20388344
Cover