Penerapan lean warehousing untuk perbaikan proses pergudangan 3pl perusahaan kimia = Application of lean warehousing for 3pl warehousing process improvement in a chemical company

Enggar Cesarini; Rahmat Nurcahyo, supervisor (Fakultas Teknik Universitas Indonesia, 2015)

 Abstrak

Dalam upaya untuk melakukan continuous improvement, sebuah perusahaan kimia berusaha untuk mencapai target warehouse service level yang belum terpenuhi dengan cara mengelola aktivitas-aktivitas pergudangan untuk dapat meningkatkan nilai tambah dan mengurangi pemborosan. Penelitian ini bertujuan untuk membuat rancangan perbaikan proses pergudangan agar dapat memenuhi target warehouse service level. Pendekatan lean warehousing serta lean tools seperti VSM, PAM, root cause analysis dan FMEA digunakan untuk menyelesaikan permasalahan terkait pemborosan yang ada dalam gudang.
Penelitian menghasilkan rancangan perbaikan proses pergudangan yang dapat menurunkan lead time proses penerimaan barang sebesar 33% dari 78.36 menit menjadi 52.2 menit dan sebesar 15% untuk proses pengeluaran barang, yaitu dari 86.52 menit menjadi 73.27 menit. Penurunan lead time tersebut berdampak pada peningkatan persentase warehouse service level sehingga mencapai target, yaitu 100%.

In effort to achieve continuous improvement, a chemical company strives to meet their warehouse service level target that have not been reached by managing their warehousing activities to increase value added and reduce waste. This research aims to make a design of warehousing process improvement in order to meet warehouse service level target. Lean warehousing approach and some lean tools such as VSM, PAM, root cause analysis and FMEA are used to solve problems related to waste, which present in the warehouse.
The research resulted in the design of warehousing process improvements that can reduce the lead time of goods receipt process by 33% from 78.36 minutes to 52.2 minutes and 15% for goods issue process, from 86.52 minutes to 73.27 minutes. Decreased lead time of the processes resulted in the increase of warehouse service level percentage to reach the target, which is 100%.

 File Digital: 1

Shelf
 S61938-Enggar Cesarini.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S61938
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2015
Bahasa : ind
Sumber Pengatalogan :
Tipe Konten :
Tipe Media :
Tipe Carrier :
Deskripsi Fisik : xiv, 81 hlm. ; ill. ; 30 cm.
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S61938 14-22-99139752 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20421496
Cover