UI - Skripsi Membership :: Kembali

UI - Skripsi Membership :: Kembali

Perbedaan biaya antara metode padat alat dan padat karya dalam pekerjaan tanah di proyek Jembatan Selanggis = Identification of cost consumption differences between heavy equipment and labor intensive method in road work at Selangis Bridge project

Dimas Adi Prasetyo; Bambang Setiadi, supervisor; Setyo Supriyadi, supervisor; Mohammed Ali Berawi, examiner; Leni Sagita Riantini, examiner (Fakultas Teknik Universitas Indonesia, 2015)

 Abstrak

Berdasarkan cara pengerjaannya, proyek dapat diklasifikasikan menjadi 2 tipe, yaitu proyek padat alat dan proyek padat karya. Kedua tipe proyek ini mempunyai efek dan kriteria yang berbeda. Dengan mengetahui lebih lanjut mengenai tipe-tipe proyek ini, proyek yang dilaksanakan dapat lebih dioptimalkan dan diefisiensikan sasaran metode pengerjaannya yang lebih baik. Contohnya, proyek padat alat dapat membantu dalam penyerapan tenaga kerja dan memakmurkan warga di sekitar proyek. Namun, waktu pengerjaan proyek padat karya akan memakan waktu yang lebih lama dari pada proyek padat alat dan akan memberikan efek kepada biaya pengerjaan proyek.
Lewat skripsi ini, penulis ingin mengetahui benefit ratio antara pengerjaan proyek padat alat dan padat karya. Hasil yang dicapai akan mengidentifikasi cara pengerjaan yang bisa memberikan lebih banyak benefit kepada semua pemangku kepentingan dalam proyek ini. Metode analisis yang dipakai menggunakan benefit ratio dan variabel perhitungannya adalah perbedaan biaya, perbedaan waktu pengerjaan, dan mean dari hasil kuesioner untuk mendukung keabsahan pernyataan awal.

Based on the work methods, a project can be classified in two different types, which are heavy equipment method and labor-intensive method. Both of these types of projects have different effects and criterion. By knowing more about these types of project, the project can be optimized more efficiently. Labor-intensive project can help people to get employed and prospering people around the project area. However, time frame of the project will be longer than heavy equipment method that can affect the cost of the project. Through this thesis, the author is trying to find the benefit ratio between heavy equipment method and labor-intensive method.
The result will indicate the urgency of those projects in remote areas, which is the way that the project is done that has the most benefit for all stakeholders. Method of analysis is uses benefit ratio theory and the calculation variables are included cost differences, time differences, and mean of the questionnaires result to support the initial statement. Result from this thesis is that the benefit ratio of price and time for the local citizens is higher when using labor-intensive method rather than heavy equipment method.

 File Digital: 1

Shelf
 S61591-Dimas Adi Prasetyo.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S61591
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2015
Bahasa : eng.
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : 133 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S61591 14-23-23768094 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20422091
Cover