Pengembangan sistem manajemen klaim proyek design and build untuk meningkatkan kinerja waktu dan biaya berbasis risk studi kasus: terminal bandara XYZ = Development of claim management system in design and build project to improve time and cost performance using risk approaches case study: terminal of XYZ airport

Christy Frisca Rambi; Yusuf Latief, supervisor; Leni Sagita Riantini, examiner; Eddy Subiyanto, examiner; Setyo Supriyadi Sipadi, examiner (Fakultas Teknik Universitas Indonesia, 2016)

 Abstrak

Proyek Terminal Bandara XYZ dibangun untuk mengatasi kelebihan kapasitas pada bandara tersebut. Proyek ini menggunakan kontrak Design and Build yang umumnya dipilih untuk efisiensi dan efektivitas pekerjaan proyek, tetapi dalam pekerjaannya masih didapati adanya klaim yang terjadi. Penelitian ini bertujuan untuk mengidentifikasi faktor-faktor yang menyebabkan klaim konstruksi pada proyek Design and Build dan mengembangkan sistem manajemen klaim untuk meningkatkan kinerja waktu dan biaya pada proyek tersebut.
Penelitian dilakukan dengan mengumpulkan data melalui survei kuesioner dan wawancara terkait proyek Design and Build. Hasil penelitian menunjukkan faktor-faktor penyebab klaim yang dominan dan ditolak oleh owner serta tindakan korektif berupa sistem manajemen klaim untuk meminimalisir klaim pada proyek konstruksi.

Project Terminal of XYZ Airport built to cope with the excess capacity at the airport. This project uses a Design and Build contract are generally chosen for the efficiency and effectiveness of project work, but during the operation there still found the claims which occurs in the process. This study aims to identify the factors that led to the claim construction on the project Design and Build and develop a claims management system to improve the performance of the time and cost of the project.
The study was conducted by collecting data via survey questionnaires and interviews related to Design and Build projects. Results shows the factors that cause the dominant claims and rejected by the owner as well as corrective measures in the form of claim management system to minimize claims on construction projects.

 File Digital: 1

Shelf
 T46655-Christy Frisca Rambi.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T46655
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2016
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xiii, 145 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T46655 15-18-682675193 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20433794
Cover