Pengukuran risiko teknis pembangunan depot pengisian pesawat udara di Sumatera Utara = Measuring technical risk for construction of aircraft fueling depot in North Sumatra

Sarah Faita Rizkiaputeri; Fauzia Dianawati, supervisor; Inaki Maulida Hakim, examiner; Romadhani Ardi, examiner; Danu Hadi Syaifullah, examiner (Fakultas Teknik Universitas Indonesia, 2017)

 Abstrak

Manajemen risiko yang buruk adalah salah satu penyebab utama kegagalan sebuah proyek. Penelitian ini membahas pengukuran risiko teknis untuk proyek pembangunan Depot Pengisian Pesawat Udara DPPU di wilayah Sumatera Utara, khususnya wilayah Silangit, Sibolga, dan Gunung Sitoli. Pengukuran risiko dilakukan untuk menyusun strategi mitigasi risiko yang harus dilakukan dalam pelaksanaan proyek. Metode pengukuran risiko dilakukan dalam empat tahapan, yaitu identifikasi risiko, pengukuran dampak dan probabilitas risiko, klasifikasi risiko, dan mitigasi risiko. Dari proses pengukuran risiko, didapatkan 65 faktor risiko yang kemudian dikelompokkan ke dalam empat kejadian risiko yaitu kerusakan sarana dan fasilitas pembangunan DPPU, keterlambatan pengerjaan pembangunan DPPU, kecelakaan kerja, dan kendala finansial. Strategi mitigasi yang diusulkan terkait dengan pemilihan jenis tangki yang digunakan, pemilihan pemasok material, kontraktor, dan moda transportasi material yang digunakan, penyediaan peralatan yang dibutuhkan, dan pelaksanaan pelatihan dan pengontrolan rutin.

Poor risk management is one of the main cause of project failure. This research is made to measure technical risk for the construction project of Aircraft Filling Depot in North Sumatra, especially Silangit, Sibolga, and Gunung Sitoli area. Risk measurement is done to create mitigation plans that need to be done in this project. The methods of measuring risk is done in four steps, which are risk identification, impact and probability measurement, risk classification, and risk mitigation. From the risk measurement process, 65 risk factors were identified and then classified to four risk events, which are facility damage, delay in construction project, work accident, and financial constrain. The proposed risk mitigation strategy includes the selection of storage tank type, selection of supplier, contractors, and material transportation method, provision of essential equipment, and implementation of routine training and monitoring.

 File Digital: 1

Shelf
 S67828-Sarah Faita Rizkiaputeri.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S67828
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2017
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xii, 57 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S67828 14-19-571899591 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20456283
Cover