Identifikasi risiko fasilitas sementara pada tahap persiapan pengeboran oleh tunnel boring machine (TBM) dalam proyek mass rapid transit (MRT) Jakarta = Risk identification of temporary facilities in excavation preparation stage by tunnel boring machine (TBM) on mass rapid transit (MRT) Jakarta project

Choirunnisa Muthi`Ah; Leni Sagita Riantini, supervisor; Ayomi Dita Rarasati, examiner; Rossy Armyn Machfudiyanto, examiner (Fakultas Teknik Universitas Indonesia, 2017)

 Abstract

Pada konstruksi MRT Jakarta, pekerjaan tunnelling dilakukan dengan menggunakan alat Tunnel Boring Machine TBM . Salah satu tahap awal pada pelaksanaan pekerjaan terowongan menggunakan TBM adalah pembangunan fasilitas sementara TBM. Penelitian ini bertujuan untuk mengidentifikasi faktor-faktor risiko pada fasilitas sementara TBM yang berpengaruh terhadap kinerja waktu proyek MRT, dampak dan penyebabnya, serta tindakan yang dapat dilakukan terhadap faktor-faktor risiko tersebut.
Penelitian dilakukan dengan mengumpulkan data melalui survey kuesioner dan wawancara. Kemudian, data tersebut diolah menggunakan uji-uji stastistik dan analisis kualitatif risiko. Hasil penelitian ini didapatkan lima faktor risiko fasilitas sementara TBM yang berpengaruh terhadap kinerja waktu proyek. Faktor risiko tertinggi pada fasilitas sementara TBM adalah ketidaksejajaran sumbu TBM dengan back anchor.

Within Jakarta MRT construction, tunnelling work done by using a Tunnel Boring Machine TBM . One of the early stages of the implementation tunnelling work using a TBM is the construction of temporary facilities for TBM. This research has purposes to identify risk factors of temporary facilities for TBM that influence time performance of MRT project, its cause and effects, and also treatment or response that can do for that risk factors.
The research was conducted by collecting data through a survey questionnaire and interview. Then, evaluated by statistics test and qualitative risk analyze. The result of this research is acquired five risk factors of temporary facilities for TBM that influence to time performance of MRT project. The highest risk of temporary facilities for TBM is misalignment of TBM axis with back anchor.

 Digital Files: 1

Shelf
 S69306-Choirunnisa Muthi'ah.pdf :: Download

LOGIN required

 Metadata

Collection Type : UI - Skripsi Membership
Call Number : S69306
Main entry-Personal name :
Additional entry-Personal name :
Study Program :
Subject :
Publishing : Depok: Fakultas Teknik Universitas Indonesia, 2017
Cataloguing Source LibUI ind rda
Content Type text
Media Type unmediated ; computer
Carrier Type volume ; online resource
Physical Description xx, 158 pages : illustration ; 28 cm + appendix
Concise Text
Holding Institution Universitas Indonesia
Location Perpustakaan UI, Lantai 3
  • Availability
  • Review
  • Cover
Call Number Barcode Number Availability
S69306 14-19-939803016 TERSEDIA
Review:
No review available for this collection: 20456871
Cover