Pengembangan standar WBS (Work Breakdown Structure) berbasis risiko untuk estimasi biaya pada proyek bendungan = Development of standardized WBS (Work Breakdown Structure)

Propezite Nurhutama Mustain; Yusuf Latief, supervisor; Leni Sagita Riantini, supervisor; Wisnu Isvara, examiner; Afrizal Nursin, examiner; Eddy Subiyanto, examiner (Fakultas Teknik Universitas Indonesia, 2019)

 Abstrak

Dalam proyek konstruksi bendungan khususnya pada proyek bendungan urugan tanah dikatakan sukses jika dilakukan pendefinisian lingkup proyek sesuai dengan persyaratan. WBS (Work Breakdown Structure) merupakan penguraian pekerjaan menjadi lebih kecil dan mudah dikendalikan. Standarisasi WBS sangat penting karena akan sangat berpengaruh terhadap estimasi biaya. Tujuan dari penelitian ini adalah mengembangkan WBS Bendungan. Metodologi yang digunakan berdasarkan peraturan Pedoman Pelaksanaan Konstruksi Bendungan Urugan Ditjen SDA (2004) dan BOQ (Bill of Quantity) proyek bendungan yang berada di Indonesia. Hasil dari penelitian ini adalah standar WBS terdiri dari 6 level dengan menganalisa variabel risiko dominan yang mungkin terjadi yang berpengaruh terhadap pengendalian biaya proyek dan pengembangan WBS standar dengan dilakukan rekomendasi respon risiko. Sebagai hasilnya, penelitian ini akan mengusulkan standar WBS yang berbasis risiko untuk proyek-proyek bendungan urugan tanah yang dapat meningkatkan estimasi biaya proyek.

Dam construction project especially earthfill dam can be successful if the scope of works is defined in accordance with the requirement. Work Breakdown Structure (WBS) divides tasks into smaller items which makes them easier to be controlled. WBS standardization has critical impact on the cost of project. The purpose of this research is to develop WBS of dam construction project. The methodology used to develop the WBS of dam is based on the regulation and guidelines related to the implementation of dam construction such as The General Specification of Earthfill Dam, Ministry of Public Works and Public Housing Indonesia (2004) and bill of quantity from earthfill dam projects in Indonesia. The research is conducted by making a questionnaire survey for dam project contractors. The output of this study is WBS standard which comprises of 6 levels by analyzing dominant risk variables that may affect project cost control and WBS standard development with risk responses recommendation. As a result, this research will propose a risk-based WBS standard for earthfill dam projects that can improve the cost estimate of the project.

 File Digital: 1

Shelf
 T51950-Propezite Nurhutama Mustain.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T51950
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2019
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xvi, 480 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T51950 15-20-224191199 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20481949
Cover