Pengembangan prosedur perencanaan dan pengendalian proyek pengeboran sumur Gas di Lapangan Gas XYZ Berbasis PMBOK 2017 untuk Meningkatkan Kinerja Waktu (Studi Kasus Proyek Pengeboran Sumur Lapangan Gas XYZ di Papua Barat) = The development of planning and controlling procedure for gas well drilling projects to improve time performance based on PMBOK 2017 (Case Study of XYZ Gas Field Well Drilling Project in West Papua)

Archivito Aryo Santoso; Yusuf Latief, supervisor; Leni Sagita Riantini, examiner; Fadhilah Muslim, examiner; Rossy Armyn Machfudiyanto, examiner (Fakultas Teknik Universitas Indonesia, 2020)

 Abstrak

Kurangnya perhatian terhadap prosedur yang tepat dalam sistem perencanaan dan pengendalian adalah salah satu penyebab utama keterlambatan banyak proyek. Dalam Proyek Eksplorasi Lapangan Gas di Papua Barat, keterlambatan adalah salah satu masalah utama yang terjadi. Keterlambatan proyek selama periode pengeboran eksplorasi menyebabkan banyak kerugian terutama terkait dengan keterlambatan dalam periode monetisasi lapangan gas tersebut, sedangkan durasi kontrak bagi hasil produksi untuk lapangan gas tersebut dengan pemerintah Indonesia tidak dapat diperpanjang dalam waktu dekat.
Penelitian ini dilakukan untuk memberikan pengembangan prosedur perencanaan dan pengendalian untuk meningkatkan kinerja waktu proyek pengeboran sumur gas di Lapangan Gas XYZ dengan menggunakan sistem keilmuan manajemen proyek berdasarkan PMBOK 2017. Metode yang digunakan dalam penelitian ini adalah analisis risiko menggunakan studi kasus operasi pengeboran eksplorasi Lapangan Gas XYZ dan juga survei untuk menentukan risiko dominan yang dapat memengaruhi kinerja waktu proyek. Selanjutnya, tindakan preventif dan korektif akan dirancang dan direkomendasikan untuk mengembangkan prosedur proyek pengeboran sumur gas sehingga kinerja waktu dapat ditingkatkan.
Hasil dalam penelitian ini menunjukkan bahwa ada tiga aspek yang diperlukan untuk pengembangan perencanaan dan pengendalian prosedur proyek pengeboran sumur di lapangan gas XYZ; sistem manajemen risiko proyek yang diterapkan pada semua fase siklus hidup proyek, penerapan Project Management Software dan dimasukkannya analisis risiko komunikasi proyek dalam sistem manajemen risiko proyek. Hasil penelitian ini dapat memberikan masukan kepada ABC Co. selaku kontraktor yang mengelola Lapangan Gas XYZ dalam menentukan dan melakukan peningkatan kinerja operasi pengeboran dan penyelesaian sumur pengembangan dan juga sumur produksi yang akan dilakukan di masa depan.

Lack of attention to proper procedures in the planning and controlling system is one of the main causes of delay of many projects. In the exploration project of gas field in West Papua, delay is one of the main problems that occur. Project delays during the exploration drilling period caused many losses mainly related to delays in the monetization period of the gas field, while the duration of the production sharing contract for the gas field with the Indonesian government cannot be extended in the near future.
This research was conducted to provide development of the project planning and control system procedures for to improve the time performance of gas wells drilling projects on the XYZ Gas Field by using project management scientific principles based on the PMBOK 2017. The method used in this research is a risk analysis using a case study of XYZ Gas Field exploration drilling operations and also a survey to determine the dominant risk that can affect time performance of the project. Furthermore, preventive and corrective actions will be designed and recommended to develop the well drilling project procedures so that time performance can be improved.
The results in this research indicate that there are three aspects needed for the development of planning and controlling procedures of well drilling projects in the XYZ gas field; the project risk management system that is applied to all phases of the project life cycle, the application of a project management software and inclusion of project communication risk analysis in the risk management system. The results of this study can provide input to ABC Co., the contractor managing the XYZ Gas Field in determining and making improvements to the performance of the drilling operation and completion of the development well and also the production well that will be carried out in the future.

 File Digital: 1

Shelf
 T-Archivito Aryo Santoso.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T-Pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2020
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xvii, 261 pages : illustration ; 28 cm. + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T-Pdf 15-21-262109050 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20503858
Cover