UI - Skripsi Membership :: Kembali

UI - Skripsi Membership :: Kembali

Dinamika faktor penghambat dan dampak proses pengadaan tanah untuk pembangunan jalan tol: Studi kasus seksi VI ruas jalan tol Cisumdawu, Kecamatan Ujungjaya, Sumedang, Jawa Barat) = Dynamics of obstacles factors and its impacts of land acquisition in toll road development (case study section 6 of Cisumdawu toll road project, Ujungjaya, Sumedang, West Java)

Aprilia Cahyani Prabudiantoro Putri; Yosef Hilarius, supervisor; Seda, Francisia Saveria Sika Ery, examiner (Fakultas Ilmu Sosial Dan Ilmu Politik Universitas Indonesia, 2020)

 Abstrak

Penelitian ini berfokus pada mengidentifikasi faktor-faktor yang menghambat proses pengadaan tanah untuk kepentingan umum yaitu pembangunan jalan tol serta dampak dari terhambatnya proses pengadaan tanah tersebut. Pengadaan tanah merupakan penghambat utama dalam percepatan pembangunan jalan tol. Studi terkait faktor-faktor yang menghambat proses pengadaan tanah untuk kepentingan umum masih terlalu berfokus pada dampaknya dan kurang mengurai simpul penyebab utama dari masalah ini. Dalam studi ini, peneliti melihat bahwa proses pengadaan tanah untuk pembangunan infrastruktur dan kepentingan ekonomi didominasi oleh negara sehingga hal tersebut dapat berdampak merugikan masyarakat. Dengan menggunakan metode kualitatif dan teknik wawancara mendalam, studi ini menemukan bahwa masalah pembagian peran dan efektifitas mekanisme kerja birokrasi menjadi hambatan utama. Di sisi lain, dampak ketidakpastian keresahan kesulitan mencari tanah pengganti, cukup banyak dialami oleh masyarakat. Secara teoritik, pengadaan tanah untuk pembangunan infrastruktur di Indonesia mencerminkan state centered development yang kurang optimal karena involusi mekanisme kerja birokrasi pemerintah sendiri. Gejala soft state masih sangat terlihat ketika negara kurang bisa melindungi masyarakat dari dampak pengadaan tanah.

This study focuses on identifying the factors that hamper the process of land acquisition process for the public interest, espescially toll road construction and the impact of the hampered land acquisition process. Land acquisition is a major obstacle in accelerating toll road development. Studies related to factors that hamper the land acquisition process are still too focused on their impact and do not examine the main causes of this problem. In this study, researchers see that the land acquisition process for the public interests is dominated by the state so that it can adversely affect the community. By using qualitative methods and in-depth interview techniques, this study found that the problem of the division of roles and the effectiveness of bureaucratic work mechanisms were the main obstacles. On the other hand, the impact of the uncertainty of anxiety on the difficulty of finding replacement land, is quite a lot experienced by the community. Theoretically, land acquisition for infrastructure development in Indonesia reflects a less than optimal state centered development due to the involution of the government's own bureaucratic work mechanism. Soft state symptoms are still very visible when the state is less able to protect the community from the effects of land acquisition.

 File Digital: 1

Shelf
 S-Aprilia Cahyani Prabudiantoro Putri.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Ilmu Sosial Dan Ilmu Politik Universitas Indonesia, 2020
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xi, 87 pages : illustration ; appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S-pdf 14-22-96460366 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20504563
Cover