Pengaruh Faktor Penyebab Keterlambatan Pada Proyek Konstruksi di Masa Pandemi COVID-19 Terhadap Kinerja Waktu dengan Metode Structural Equation Modeling Pada Masa New Normal = Factors Causing Delay in Construction Projects During The COVID-19 Pandemic on Time Performance Using Structural Equation Modeling Method During New Normal Period

Fajar Nur Pangestu; Rossy Armyn Machfudiyanto, supervisor; Fadhilah Muslim, examiner; Rully Andhika, examiner (Fakultas Teknik Universitas Indonesia, 2021)

 Abstrak

Pada Bulan April 2020 lebih dari 20% proyek konstruksi di Eropa, Timur Tengah dan Afrika ditunda hingga dibatalkan akibat memuncaknya pandemi COVID-19. Salah satu proyek dalam negeri yang mengalami keterlambatan akibat pandemi COVID-19 adalah pembangunan PLTA Jatigede di Kabupaten Sumedang. Pengerjaan proyek ini sempat terhenti tanpa adanya kegiatan selama 6 bulan akibat pandemi COVID-19. Terdapat 3 (tiga) tujuan dalam penelitian ini, diantaranya adalah: (1) Mengidentifikasi faktor - faktor yang mempengaruhi keterlambatan proyek konstruksi pada masa pandemi COVID-19 di Indonesia; (2) Menganalisis bentuk hubungan antar faktor keterlambatan proyek konstruksi pada masa pandemi COVID-19 untuk meningkatkan kinerja waktu pada masa New Normal dan (3) Mengembangkan strategi untuk meningkatkan kinerja waktu proyek konstruksi pada masa New Normal. Metode yang digunakan dalam penelitian ini adalah validasi terhadap 3 pakar dan survei terhadap 31 responden menggunakan Structural Equation Modeling dengan aplikasi SMARTPLS. Hasil dari penelitian ini adalah didapatkan 11 (sebelas) variabel yang berpengaruh terhadap keterlambatan proyek konstruksi pada masa pandemi, diantaranya adalah: (1) owner; (2) konsultan; (3) kontraktor; (4) designer; (5) tenaga kerja; (6) material; (7) peralatan; (8) eksternal; (9) financial; (10) sosial – politik; (11) project. Nilai R-Square untuk variabel kinerja waktu sebesar 0.875. Variabel yang memiliki pengaruh dengan tingkat signifikansi tinggi terhadap kinerja waktu adalah variabel konsultan. Nilai T-Statistics untuk hubungan tersebut sebesar 2.62. Variabel konsultan tersebut dipengaruhi dengan tingkat signifikansi tinggi oleh variabel owner dengan nilai T-Statistics sebesar 8.58. Terdapat 5 strategi utama yang perlu dilakukan untuk meningkatkan kinerja waktu proyek konstruksi pada masa New Normal diantaranya adalah dengan: (1) Menerapkan protokol kesehatan yang ketat; (2) Menerapkan digital construction dan mengadakan pertemuan intensif baik secara online maupun offline; (3) Menetapkan prosedur terkait koordinasi dan pengawasan sesuai dengan peraturan yang berlaku serta melakukan monitoring secara periodik; (4) Mematangkan setiap keputusan yang akan dibuat; (5) Menetapkan standar komunikasi dan koordinasi dengan seluruh stakeholder yang terlibat.

In April 2020, more than 20% of the construction project in Europe, the Middle East, and Africa were postponed even canceled due to the peak of the COVID-19 case number. One of the local projects that must be delayed due to the COVID-19 pandemic is Jatigede Hydropower Construction Plant in Sumedang Regency. The construction work had stopped without any activities for 6 months due to the pandemic. There are 3 (three) objectives of this study, including (1) Identify the factors that affect the delay of Indonesia’s construction project during the COVID-19 pandemic; (2) Analyze the relation between any delay factors on a construction project during the COVID-19 pandemic to improve the time management performance during the New Normal period and (3) Develop strategies to improve construction project time management performance during the New Normal Period. The method that used in this study is a validation of 3 experts and surveys towards 31 respondents using Structural Equation Modeling with SMARTPLS application. The results of this study obtain 11 (eleven) variables that affect the delay of construction project during the pandemic, including: (1) owner; (2) consultant; (3) contractors; (4) designers; (5) manpower; (6) materials; (7) equipment; (8) external; (9) finances; (10) social-political; (11) projects. The R-Square value for the time performance variable is 0.875. The variable that influences with a high level of significance on-time performance is the consultant variable. The value of T-Statistics for this relationship is 2.62. The consultant variable is influenced with a high level of significance by the owner variable with a T-Statistics value of 8.58. 5 main strategies need to be implemented to improve construction project time performance during the New Normal period including: (1) Implementing strict health protocols; (2) Implementing digital construction and holding intensive meetings both online and offline; (3) Establish procedures related to coordination and supervision by applicable regulations and conduct periodic monitoring; (4) Finalizing every decision to be made; (5) Establish communication and coordination standards with all stakeholders involved.

 File Digital: 1

Shelf
 S-Fajar Nur Pangestu.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Skripsi Membership
No. Panggil : S-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2021
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource (rdcarrier)
Deskripsi Fisik : xix, 212 pages : illustration + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
S-pdf 14-23-82971228 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20526018
Cover