Implementasi Manajemen Pelaksanaan Waktu Dan Biaya Di Pembangunan Bendungan Bener Paket 4 Myc = Implementation Of Time And Cost Management In The Bener Dam Construction Project 4 Myc

Donny Bangkit Ariwibowo; Jaka Fajar Fatriansyah, supervisor; Eko Adi Nugroho, supervisor; Sutrasno, examiner (Fakultas Teknik Universitas Indonesia, 2022)

 Abstrak

Proyek Pembangunan Bendungan Bener Paket 4 yang dilaksanakan oleh PT. Adhi Karya (Persero) TBK. merupakan bagian dari Proyek Strategi Nasional National. Praktik Keinsinyuran kali ini adalah mengevaluasi penyelenggaraan Earned Value Management. Batasan pada penelitian ini adalah 1. Data yang digunakan adalah data Proyek Pembangunan Bendungan Bener Paket 4. 2. Data cashflow berdasarkan laporan keuangan Proyek Pembangunan Bendungan Bener Paket 4. 3. Pengamatan dilakukan dari awal proyek hingga akhir proyek (berdasarkan data laporan bulanan dan time schedule. 4. Penelitian hanya dikhususkan pada masalah kinerja biaya dengan metode earned value concept. Berdasarkan analisis dan pembahasan yang telah dilakukan, dari awal proyek sampai dengan bulan November 2021 kinerja biaya proyek tidak baik faktor utama yang berpengaruh terhadap indeks kinerja biaya proyek adalah akibat biaya langsung maupun biaya tidak langsung yang dikeluarkan sedangkan realisasi progress belum berjalan baik di proyek. Hal ini yang menyebabkan nilai ACWP lebih besar dari BCWP sehingga kinerja biaya proyek di awal menjadi tidak baik karena nilai CPI < 1. Sedangkan mulai bulan Desember 2021 sampai dengan Oktober 2022 kinerja biaya proyek sudah baik ditunjukkan dengan nilai CPI >1.

Bener Dam Construction Project package 4 implemented by PT. Adhi Karya (Persero) TBK. is part of the National Strategy Project. This Engineering Practice is evaluating the implementation of Earned Value Management. The limitations of this study are 1. The data used are data from the Bener Dam Package 4 Construction Project. 2. Cash flow data is based on the financial reports of the Bener Dam Package 4 Construction Project. 3. Observations were made from the beginning of the project to the end of the project (based on monthly report data and time schedule 4. This research is only devoted to the issue of cost performance using the earned value concept method Based on the analysis and discussion that has been carried out, from the start of the project to November 2021 the project cost performance was not good. The main factor influencing the project cost performance index is due to cost direct and indirect costs incurred while the realization of progress has not gone well in the project. This is what causes the ACWP value to be greater than the BCWP so that the initial project cost performance is not good because the CPI value is < 1. Meanwhile from December 2021 to October 2022 the project's cost performance has shown good d with a CPI value > 1.

 File Digital: 1

Shelf
 PR-Donny Bangkit Ariwibowo.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tugas Akhir
No. Panggil : PR-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2022
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xiii, 61 pages : illustration + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
PR-pdf 16-23-22223832 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920516798
Cover