UI - Tugas Akhir :: Kembali

UI - Tugas Akhir :: Kembali

Perencanaan dan Pelaksanaan Pekerjaan Retrofitting pada Existing 6kV Medium Voltage Switchgear PT. South Pacific Viscose = Planning and Implementation of Retrofitting Work on Existing 6kV Medium Voltage Switchgear PT. South Pacific Viscose

Dhanang Tri Laksono; Catur Apriono, supervisor; Asruldi Azis, supervisor (Fakultas Teknik Universitas Indonesia, 2023)

 Abstrak

PT. South Pacific Viscose (SPV) memproduksi serat viscose staple fibre (VSF) pada 5 line produksi di Plant Purwakarta. Setiap line produksi tersebut memerlukan air sebagai bahan dalam pengolahannya, dan limbah air dihasilkan sebagai produk yang harus dibuang. Maka dari itu penambahan kapasitas Waste Water Treatment dilakukan untuk mengimbangi kenaikan produksi dari tiap line produksi sebagai HARUM Project. Dari pekerjaan penambahan tersebut, perencanaan dan implementasi dari sisi electrical perlu diperhatikan. Implementasi pekerjaan yang ada di lapangan dilakukan pengetesan setelah pemasangan, dan setiap komponen yang diinstalasi lolos dalam commissioning test sesuai dengan standard yang digunakan. Untuk langkah-langkah pekerjaan dianalisis terhadap Kode Etik Insinyur, Asas Profesionalisme, dan Keselamatan, Kesehatan Kerja, dan Lingkungan (K3L). Rangkaian pekerjaan yang sudah dilakukan di HARUM Project sudah memenuhi standar penilaian yang menjadi acuan analisis di dalam laporan praktik keinsinyuran ini. Namun dari segi aspek K3L masih perlu menjadi perhatian dalam pelaksanaan pekerjaannya. Sehingga, dalam kegiatan untuk future project kedepannya, aspek yang menjadi koreksi pada laporan praktik keinsinyuran ini dapat menjadi bahan pertimbangan nantinya.

PT. South Pacific Viscose (SPV) produces viscose staple fiber (VSF) in 5 production lines at the Purwakarta Plant. Each of these production lines requires water as an ingredient in its processing, and waste water is produced as a product that must be disposed of. Therefore, the addition of Waste Water Treatment capacity is carried out to offset the increase in production from each production line as the HARUM Project. From the additional work, planning and implementation from the electrical side need to be considered. Implementation of existing work in the field is tested after installation, and each installed component passes the commissioning test in accordance with the standards used. The work steps are analyzed against the Engineer's Code of Ethics, Principles of Professionalism, and Occupational Health, Safety, and Environment (K3L). The series of works that have been carried out at the HARUM Project have met the assessment standards which are the reference for analysis in this engineering practice report. However, in terms of K3L aspects, it still needs to be considered in the implementation of its work. Thus, in activities for future projects in the future, aspects that become corrections in this engineering practice report can be taken into consideration later.

 File Digital: 1

Shelf
 TA-Dhanang Tri Laksono.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tugas Akhir
No. Panggil : TA-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2023
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xii,47 pages : illustration
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
TA-pdf 16-23-80348929 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920525765
Cover