UI - Tugas Akhir :: Kembali

UI - Tugas Akhir :: Kembali

Pekerjaan Penggantian Accoustic Ceiling Menjadi Sandwich Panel Pada Proyek Yakult Sukabumi = The Replacement Work Of Accoustic Ceiling Into Sandwich Panel Material At Yakult Sukabumi Project

Riski Aditya; Heru Purnomo, supervisor; Yusuf Latief, examiner (Fakultas Teknik Universitas Indonesia, 2024)

 Abstrak

Pada tahun 2023 PT. Yakult Indonesia Persada melakukan perbaikan di area pabriknya yang berada di Desa Pesawahan Cicurug Sukabumi, Jawa Barat. Salah satunya adalah penggantian ceiling pada area moulding room. Existing ceiling pada area tersebut menggunakan material akustik diganti menjadi material sandwich panel agar ruangan menjadi lebih kedap dan kebersihannya mudah dikontrol. PT. Takenaka Indonesia dimana penulis bekerja sebagai site engineer ditunjuk sebagai kontraktor yang melaksanakan proyek tersebut dengan durasi pengerjaan 12 bulan. Adapun metode pekerjaan yang dilakukan adalah menggunakan sistem temporary stage sehingga memisahkan antara area produksi owner dan area kerja konstruksi. Temporary stage yang digunakan menggunakan rangka baja UNP yang diatasnya ditumpangi sandwich panel dengan tebal 50 mm sebagai lantai kerjanya. Setelah temporary stage selesai dipasang, tahap selanjutnya adalah melakukan pembongkaran existing ceiling, pemasangan ceiling hanger UNP dan pemasangan ceiling baru berupa material sandwich panel PIR dengan tebal 100 mm dengan metode slip joint. Dengan menetapkan standard kerja yang tinggi, PT. Takenaka Indonesia juga berkomitmen untuk menjaga aspek safety dalam setiap proses kerjanya. Hal ini dibuktikan dengan melakukan toolbox meeting, penyediaan alat P3K & klinik serta melakukan simulasi tanggap darurat gempa bumi. Selain itu pihak kontraktor juga menjunjung tinggi integritas kerja dengan menaati kode etik keinsinyuran yang berlaku. Sehingga, pekerjaan bisa selesai dengan tepat waktu dan dengan kualitas yang baik.

In 2023, PT. Yakult Indonesia Persada made improvements to its factory area located in Pesawahan Village, Cicurug, Sukabumi, West Java. One of them is replacing the ceiling in the molding room area. The existing ceiling in the area uses acoustic material replaced with sandwich panel material so that the room becomes more soundproof and its cleanliness is easy to control. PT. Takenaka Indonesia, where the author works as a site engineer, was appointed as the contractor to carry out the project with a duration of 12 months. The work method used is to use a temporary stage system so as to separate the owner's production area and the construction work area. The temporary stage used uses a UNP steel frame with a 50 mm thick sandwich panel as its working floor. Furthermore, the existing ceiling was dismantled, the UNP ceiling hanger was installed, and a new ceiling was installed in the form of a 100 mm thick PIR sandwich panel using the slip joint method. By setting high work standards, PT. Takenaka Indonesia is also committed to maintaining safety aspects in all its work. This is evidenced by holding toolbox meetings, providing first aid kits & clinics, and conducting earthquake emergency response simulations. In addition, the contractor also upholds work integrity by complying with the applicable engineering code of ethics. So, the work is completed on time and with good quality.

 File Digital: 1

Shelf
 PR-Riski Aditya.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tugas Akhir
No. Panggil : PR-PDF
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2024
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : 86 pages : illustration
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
PR-PDF 16-25-82159097 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920543743
Cover