Pengembangan Strategi Pengadaan Barang Jasa Berbasis Risiko pada Proyek Pembangunan di Kawasan Inti Pusat Pemerintahan Ibu Kota Nusantara dengan Pendekatan Design and Build = Development of Risk-Based Procurement Strategies for Construction Projects in the Central Government Core Area of the Nusantara Capital City Using a Design and Build Approach

Angga Wahyu Pratama; Wisnu Isvara, supervisor; Rossy Armyn Machfudiyanto, examiner; Rully Adhika, examiner; Mustika Sari, examiner (Fakultas Teknik Universitas Indonesia, 2024)

 Abstrak

Pelaksanaan yang cepat dan kebutuhan mendesak akan infrastruktur merupakan alasan utama mengapa banyak proyek di Kawasan Inti Pemerintahan menggunakan metode design and build untuk konstruksi di ibu kota baru, Nusantara. Namun, keterlambatan sering terjadi selama tahap implementasi. Tesis ini menyelidiki faktor-faktor risiko yang mempengaruhi waktu pelaksanaan proyek-proyek design and build. Variabel-variabel yang relevan dikumpulkan dari data sekunder dan studi literatur, kemudian divalidasi oleh para ahli, dan kuesioner didistribusikan kepada responden. Variabel-variabel tersebut selanjutnya dievaluasi menggunakan analisis risiko kualitatif. Dari 100 faktor risiko yang disurvei, 16 diidentifikasi sebagai yang paling kritis: (X5) (X6) perkiraan biaya yang tidak akurat selama fase perencanaan, (X8) Urban Plan berubah, (X9) (X47) investigasi situs yang tidak memadai atau kondisi tanah dan permukaan yang tidak terduga, (X26) kelayakan finansial kontraktor, (X54) (X56) keterlambatan pengiriman peralatan dan bahan konstruksi, (X55) (X75) akses situs yang sulit atau terbatas termasuk faktor cuaca, (X57) (X59) kelangkaan tenaga kerja dan bahan konstruksi, (X61) (X63) perubahan desain atau lingkup pekerjaan selama pelaksanaan atas permintaan pemilik, (X62) kompleksitas dan ukuran proyek yang besar, dan (X70) lahan yang belum bebas.

The rapid execution time and the immediate necessity of the infrastructure are the reasons why many projects in the Core Governmental Area utilize the design and build method for construction in the new capital city, Nusantara. However, delays frequently occur during implementation. This thesis explores the risk factors affecting the project execution time of design and build projects. Variables were compiled from secondary data and literature studies, validated by experts, and questionnaires were distributed to respondents. These were then evaluated using qualitative risk analysis. From the 100 risk factors surveyed, 16 were identified as the most critical: (X5) (X6) inaccurate cost estimation during the planning phase, (X8) changes in urban planning, (X9) (X47) inadequate site investigation/unexpected ground/surface conditions, (X26) financial feasibility of the contractor, (X54) (X56) delayed delivery of construction equipment and materials, (X55) (X75) difficult/limited site access including weather-related factors, (X57) (X59) scarcity of labor and construction materials, (X61) (X63) design or scope changes during implementation at the owner's request, (X62) complexity and large project size, and (X70) unacquired land.

 File Digital: 1

Shelf
 T-Angga Wahyu Pratama.pdf :: Unduh

LOGIN required

 Metadata

Jenis Koleksi : UI - Tesis Membership
No. Panggil : T-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Program Studi :
Subjek :
Penerbitan : Jakarta: Fakultas Teknik Universitas Indonesia, 2024
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated
Tipe Carrier : online resource
Deskripsi Fisik :
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
  • Sampul
No. Panggil No. Barkod Ketersediaan
T-pdf 15-24-66356474 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920545223
Cover