Renanta Muchlis Budijanto
"In Order to increase the quality of project implementation much research will need to be carried out in Indonesia and abroad. In 1982 The Business Roundtable's team in the US found that opportunities to reduce project costs and schedules by using existing and new construction technology are lost because construction too often is relegated to operate as a produstion function separated from financial planning, scheduling, and engineering or architectural design. The Construction Industry Institute's (CIT) Task Force defines this term as Constructability, which is the optimum integration of construction knowledge and experience in planning, engineering, proqurement, and field operations to achieve overall project objectives.
As the customer, the owner gets what he insist on. As the leader of the project team, the owners plays a vital role in using constructability to meet project objectives. Specific project documenting the constructability effort have shown that owners accrued an average reduction in total project cost of 4.3% and in project schedule of 7.5%. These savings represented a 10- to-1 return on the owner's investment in constructability. Altough significant saving can result, the opportunities available are often overlooked by owners.
This research was conducted to study the role of project owners for implementing constructability improvement during conceptual planning phase which leads to an improven project time performance of construction project in Jabotabek Area. A questionnare survey was used as the method for collecting data. Statistical analysis was performed to analyse the data and to develop a regression model between the role of project owners for constructability improvement during conceptual planning pQase and the performance of construction project's schedule.
The result of this study shows a positive tinier correlation between the project owner's role for constructability improvement during conceptual planning phase and the project time performance. The main variables are assuring that key individual assigned to the project team each have appropriate experience with the project and clearly state the priority of the project objectives."
Depok: Fakultas Teknik Universitas Indonesia, 2001
T40619
UI - Tesis Membership  Universitas Indonesia Library
cover
Renata Muchlis Budijanto
"In Order to increase the quality of project implementation much research will need to be carried out in Indonesia and abroad. In 1982 The Business Roundtable's team in the US found that opportunities to reduce project costs and schedules by using existing and new construction technology are lost because construction too often is relegated to operate as a production function separated from financial planning, scheduling, and engineering or architectural design. The Construction Industry Institute's (CII) Task Force defines this term as Constructability, which is the optimum integration of construction knowledge and experience in planning, engineering, procurement, and field operations to achieve overall project objectives.
As the customer, the owner gets what he insist on. As the leader of the project team, the owners play a vital role in using constructability to meet project objectives. Specific project documenting the constructability effort have shown that owners accrued an average reduction in total project cost of 4.3% and in project schedule of 7.5%_ These savings represented a 10-to-1 return on the owner's investment in constructability. Although significant saving can result, the opportunities available are often overlooked by owners.
This research was conducted to study the role of project owners for implementing constructability improvement during conceptual planning phase which leads to an improve project time performance of construction project in Jabotabek Area. A questionnaire survey was used as the method for collecting data. Statistical analysis was performed to analyze the data and to develop a regression model between the role of project owners for constructability improvement during conceptual planning phase and the performance of construction project's schedule.
The result of this study shows a positive linier correlation between the project owner's role for constructability improvement during conceptual planning phase and the project time performance. The main variables are assuring that key individual assigned to the project team each have appropriate experience with the project and clearly state the priority of the project objectives."
Depok: Fakultas Teknik Universitas Indonesia, 2001
T1141
UI - Tesis Membership  Universitas Indonesia Library
cover
cover
Dwie Suksmono Hadhi
"The Influence of Improving Constructability during The Design Phase on the Performance of Construction Project Schedule in Indonesia
Constructability as defined by Construction Industry Institute, Constructability Concepts File, The University of texas at Austin as; the optimum use of construction knowledge and experience during the phases of planning, designing, procurement and construction to achieve the project goal. Constructability involves the thought of how to build a project even before it is designed.
Currently there are three issues which dominate constructability applications; design, layout, and construction method. In order to obtain deeper understanding of the potential application of Constructability for Construction Project implementation, the research focussed on the effect of its key characteristics introduced during the design phase on the performance of Construction Schedules in Indonesia.
Data was obtained through questionnaires from project architects and structural engineers of Consultants in 24 Construction Projects executed during the last decade between 1985 - 1995. Correlation and multiple regression analysis were utilized to establish models on the relation between Constructability variables and Construction Schedule Performance. The degree of completing construction projects as measured by actual against planned time performance proved to be related to Constructability variables in a linear manner.
From the analysis of 48 prospective explanatory Constructability variables during the design phase identified three determinants influencing Construction Schedule Performance. The three significant Constructability variables were; to confirm the filing system (x23), to describe the pre-fabrication system (x43), and to define clearly the contractor limit in design document (x12).
Further research provided additional evidence of the existence of Constructability characteristics through dummy variables which were; to eliminated weather problem (x46)."
Depok: Fakultas Teknik Universitas Indonesia, 2000
T2897
UI - Tesis Membership  Universitas Indonesia Library
cover
Sugih Pranoto Aji
"In order to increase the quality of Project implementation much research will need to be carried out in Indonesia and abroad. In 1960 the Government of UK identified many construction projects that were not able to increase the communication and coordination between the design and construction phase. The concept of build ability arose in 1979 in order to enhance the design process by inputting the construction method during the design phase. The Construction Industry Research Information Association (CIRIA) has defined build ability as follows: "the extent to which the design of a building facilitates ease of construction, subject to overall requirements for the completed building?.
Project (CICE) researched into the increasing of quality, efficiency, productivity and cost effectiveness in the construction projects. The research estimates that constructability improvements saved at least 10-20 times the cost of the constructability effort. The Construction Industry Institute, Austin, USA in 1986 defined constructability as ?the optimum use of construction knowledge and experience in planning, engineering, procurement and field operations to achieve overall project objectives?.
The research, which is a partial requirement for a Master degree in construction management at the University of Indonesia, was aimed at understanding the coordinating position and influence of the owner of projects for improving constructability during conceptual planning phase.
The research proceeded to study into the impact of owner contribution for improving constructability during conceptual planning phase. In order to further understand such owner contribution, its impact on project construction cost performance was measured and quantified.
Data of projects constructed in Indonesia were then obtained through questionnaires from official owner representatives of companies hi Jakarta. Variables in the questionnaire which represented owner quality contribution were then correlated to the same project cost performance variable.
In depth analysis of the correlation were then carried out to build regression models of the relationship between quality of owner contribution during conceptual planning phase to project cost performance.
The statistical including validation test needs were also carried out in order to provide the guidelines for increasing knowledge in constructability for future projects in Indonesia.
"
Depok: Fakultas Teknik Universitas Indonesia, 2000
T666
UI - Tesis Membership  Universitas Indonesia Library
cover
Simanjuntak, Sheba Hartaty
"Bangunan konstruksi dapat menghasilkan rancangan yang baik, bila awalnya telah dipikirkan bagaimana cara membangunnya. Kegagalan konsultan perencana memperkirakan bagaimana suatu rancangan dibangun oleh kontraktor dapat menyebabkan permasalahan yang menimbulkan kenaikan biaya dan keterlambatan jadwal pelaksanaan konstruksi. Permasalahan tersebut dapat diselesaikan dengan constructability yaitu dengan melibatkan tenaga ahli konstruksi yang berpengetahuan dan berpengalaman untuk ikut serta dan memberi masukan pada tahap perancangan. Hal ini lebih menjamin agar rancangan disusun dengan menggunakan metode dan teknologi yang dapat diterapkan oleh kontraktor.
Penelitian ini dilakukan dengan mengirimkan kuesioner ke berbagai perusahaan konsultan perencana yang berada di wilayah Jabotabek. Dan hasil penyebaran kuesioner diperoleh 30 kuesioner dan 50 kuesioner yang diterima kembali untuk dianalisis dengan menggunakan program SPSS.
Hasil analisis dengan model regresi berganda dapat menggambarkan adanya hubungan korelasi positif yang sangat kuat antara variabel-variabel peningkatan constructability pada perancangan oleh konsultan perencana dengan kinerja biaya. Model regresi berganda terdiri dari 3 (tiga) variabel penentu yang mempengaruhi kinerja biaya berdasarkan penilaian terhadap sampel dan koordinator proyek dari perusahaan konsultan perencana, yaitu :
1. Menyesuaikan pendekatan rancangan dengan metode konstruksi,
2. Mendefinisikan secara jelas batasan kontraktor dalam dokumen perancangan, dan
3. Secara aktif meminta masukan dari personil konstruksi pada setiap tahapan dan proses perancangan.
Dan hasil penelitian ini, peningkatan constructability pada perancangan dapat digunakan untuk menghasilkan kualitas rancangan yang dapat meningkatkan kinerja biaya pada pelaksanaan proyek-proyek konstruksi di Indonesia di masa mendatang.

Influence of Constructability Improvement in Design Phase to Project Cost Performance of Construction Projects in IndonesiaConstruction building could to products a good design, if the early to think how in manner to be constructed. Failure of designer to consider how the design should be implemented by contractor can result in scheduling problems and delays during the construction process. That problems could be solved with constructability namely by the construction expert involved who had knowledge and experience to joint and seek construction input in design. This has more to warrant in order that design to arrange by using technology and method that could apply of contractor.
This research has done in the designer companies with sent some questionnaires to several of designer companies in Jabotabek. From questionnaires spread result 30 from 50 questionnaires received to be viable analysis with used SP SS program.
The result of multiple regression analysis model shows that influence constructability improvement in design of designer will improving project cost performance. Multiple regression models has 3 of key variables influencing in cost performance carried out by estimates from persons of construction expert or project coordinator in designer's firm are:
(1) Integrate design approach with construction method,
(2) Clearly define contractor interface in the design document, and
(3) Actively seek construction input to all stages of the design process.
From these research resulted, construction improvement in design can be used to obtain the quality of design result that cost performance can be improvement in operation of projects construction in the future of Indonesia construction project.
"
Depok: Fakultas Teknik Universitas Indonesia, 2000
T-Pdf
UI - Tesis Membership  Universitas Indonesia Library
cover
Erman Surya Bakti
"Meningkatnya persaingan dan tuntutan efisiensi pada industri konstruksi menuntut adanya pengendalian mutu yang dikombinasikan dengan aspek ekonomis dan jadwal proyek. Hal ini memotivasi berbagai penelitian yang menghasilkan teknik-teknik peningkatan mutu dan efisiensi/efektifitas dari sebuah proyek seperti total quality management, value engineering, designability, contractability, constructability, operability, maintainability dan sebagainya. Penelitian ini bertujuan untuk mengetahui dan menganalisa salah satu peningkatan mutu proyek konstruksi yaitu penerapan peningkatan constructability pada tahap perencanaan dan perancangan proyek. Pendekatan ini dilakukan karena besarnya pengaruh perencanaan dan perancangan terhadap kualitas, biaya dan waktu pelaksanaan proyek secara keseluruhan. Pelaksanaan penelitian studi kasus ini dilakukan pada sebuah perusahaan nasional yang bergerak di bidang industri konstruksi dengan pola design and build dimana penelitian difokuskan pada pemahaman, pelaksanaan, keuntungan, dan hambatan constructability di perusahaan tersebut dan dua buah proyek yang dijadikan studi kasus. Jenis penerapan constructability secara informal yang didapat pada studi kasus ini diindikasikan oleh tidak adanya prosedur tertulis tentang constructability, rendahnya tingkat lesson learned, tidak adanya koordinator constructability yang ditunjuk secara resmi, masih banyaknya hambatan pelaksanaan dan tidak adanya pencatatan kinerja constructability. Walaupun demikian pada pelaksanaan constructability secara informal ini, bahwa penerapan constructability pada tahap perencanaan dan perancangan terbukti meningkatkan kinerja proyek konstruksi, dengan variabel yang paling berpengaruh adalah penjadwalan berdasarkan construction sensitive dan fasilitas desain dalam mengefisienkan konstruksi."
Depok: Fakultas Teknik Universitas Indonesia, 2002
T1106
UI - Tesis Membership  Universitas Indonesia Library
cover
Mitha Hasti Suryani
"Proyek konstruksi mengandung unsur ketidakpastian, dan memiliki risiko tinggi sehingga dapat mempengaruhi kinerja biaya. Dalam menangani risiko diperlukan analisis risiko sebagai pendekatan profesional yang diperlukan sebelum menerapkan manajemen risiko.
Identifikasi risiko yang merupakan langkah awal dari analisis risiko dilakukan untuk memperoleh sumber-sumber risiko yang mempengaruhi kinerja biaya proyek. Adapun sumber-sumber risiko diperoleh dari referensi-referensi yang terkait. Untuk mendapatkan risiko yang dominan, maka dilakukan estimasi terhadap sumber-sumber risiko. Pada tahap ini, digunakan analisis statistik dengan bantuan SPSS 9.01 untuk mengolah sampel yang diperoleh dari penyebaran kuesioner. Berdasarkan analisis statistik ini diperoleh variabel-variabel sumber risiko yang paling dominan terhadap kinerja biaya proyek, yaitu change order, dan jenis dan jumlah material yang diperlukan/tersedia. Selain variabel tersebut variabel-variabel lain yang belum teridentifikasi tetapi mempengaruhi kinerja biaya proyek, yaitu kualitas klausul kontrak yang dapat menimbulkan perselisihan, dan kesalahan/kekurangan estimasi.
Jumlah sampel yang diperoleh belum memadai, sehingga tidak dapat menggambarkan kondisi kinerja biaya akibat dari risiko yang terjadi dalam proyek. Untuk itu perlu dilakukan estimasi lebih lanjut terhadap sumber risiko yang dominan, yaitu dengan analisis probabilitas yang menggunakan teknik simulasi Monte Carlo. Variabel-variabel acak sumber risiko dijadikan input dalam model regresi, sehingga didapat kriteria kinerja biaya proyek. Melalui simulasi ini diperoleh gambaran pengaruh dari sumber risiko terhadap kinerja biaya yang mendekati kenyataan sebenarnya di lapangan.
Evaluasi risiko merupakan langkah selanjutnya dari analisis risiko. Teknik yang digunakkan dalam mengevalusi risiko adalah dengan mensimulasi Net Present Value yang diperoleh dari analisis cash flow proyek. Metoda yang diterapkan ini merupakan gabungan dari NPV dan risiko yang terjadi dalam proyek. Dalam penelitian ini, material/peralatan import yang dipengaruhi oleh perubahan nilai tukar USD terhadap rupiah, menjadi input sumber risiko dalam evaluasi proyek. Evaluasi risiko proyek diperlukan untuk menentukan alternatif strategi pembelian material/peralatan import dan rentang probabilitas NPV yang memiliki kemungkinan besar bagi kontraktor untuk mendapatkan profit.
Hasil dari simulasi NVP menunjukkan bahwa skenario pembelian semua material/peralatan import pada bulan pertama pelaksanaan proyek memiliki probabilitas kerugian terbesar, dan skenario pembelian perbulan memiliki probabilitas kerugian terkecil. Kedua skenario ini menjadi rentang probabilitas NPV yang merupakan baseline bagi kontraktor dalam melakukan strategi pembelian material/peralatan import."
Depok: Fakultas Teknik Universitas Indonesia, 2001
T8816
UI - Tesis Membership  Universitas Indonesia Library
cover
Asdyantoro Manubowo
"Klaim antara pihak-pihak yang terkait dalam proyek konstruksi adalah hal yang sering terjadi dalam pelaksanaan pekerjaan. Klaim akan dapat menyebabkan terhambatnya pelaksanaan pekerjaan di proyek konstruksi apabila tidak mendapat penanganan yang baik dari masing-masing pihak yang terkait. Untuk itu perlu dicari cara untuk mengidentifikasi faktor-faktor penyebabnya sehingga diharapakan dapat menghindari atau meminimalkan dari kemungkinan terjadinya klaim tersebut.
Tujuan tesis ini adalah untuk mengetahui seberapa besar hubungan yang berpengaruh nyata antara pengaruh klaim terhadap kinerja waktu kontraktor untuk proyek-proyek bangunan bertingkat di wilayah Jabotabek. Hasil dari penelitian ini yang menggunakan analisis stastitik terhadap sample proyek dalam bentuk kuisioner memperlihatkan hasil yang menyatakan bahwa adanya klaim dengan variabel penentu yang mewakili variabel lainnya mempunyai tingkat kesesuaian sebesar 84,4% terhadap variabel kinerja waktu proyek dengan model persamaan linear dengan 2 variabel penentunya adalah, pembayaran termin yang terlambat dan perhitungan struktur dan disain bangunan yang tidak tepat."
Depok: Fakultas Teknik Universitas Indonesia, 2002
T4305
UI - Tesis Membership  Universitas Indonesia Library
cover
Ismail
"Proyek konstruksi adalah proyek yang berkaitan dengan upaya pernbangunan suatu bangunan infrastmktur, yang umurnnya mencakup pekeljaan pokok yang termasuk dalam bidang teknik sipil dan arsitektur. Pekezjaan konstruksi memberikan tantangan yang bersifat khusus karena hampir setiap konstruksi bangunan apapun macamnya selalu direncanakan atau dilaksanakan dengan menggunakan sistern rekayasa tertentu yang khusus diperuntukkan bagi bangunan tersebut. Hampir tidak pernah ditemui struktur suatu bangunan yang tepat sama atau merupakan duplikasi dari bangunan lainnya.
Penggunaan Manajer Proyek sangat berguna bagi perusahaan jasa konstruksi, sehingga dapat mengendalikan tenaga dan sumber daya yang ada dilapangan menjadi efektif dan produktitf Manajer Proyek merupakan organisator dan koordinator proyek yang bertanggung jawab atas pelaksanaan proyek secara keseluruhan baik secara teknis maupun administratimi keuangan dan lingkungan. Manajer Proyek bertugas memimpin, mengarahkan dan mengendalikan pelaksanaan proyek, selanjutnya juga bertanggung jawab atas terselenggaranya pelaksanaan proyek sesuai dengan sistem manajemen proyek yang disetujui pemilik proyek. Dengan tujuan agar proyek menmpai sasaran tepat waktu, mutu, biaya serta aman dalam pelaksanaan.
Tujuan dari penelitian ini adalah melihat adanya huhungan secara kuantitatif melalui analisis statistik peran dari Manajer proyek terhadap kinerja akhir dari pelaksanaan proyek konstruksi. Kinerja yang akan diamati adalah kinerja waktu, sedangkan proyek konstruksi yang dijadikan :ampel adalah proyek bangunan gedung bertingkat yang berada di wilayah Jabotabek. Pengumpulan data dilakukan dengan menggunakan kuesioner yang ditujukan kepada Manajer Proyek.
Setelah dilakukan analisis secara statistik dapat diperlihatkan suatu hasil yang menyatakan bahwa peran Manajer Proyek untuk meningkatkan kinerja waktu dengan model persamaan non linier dan variabel-variabel penentu adalah melaporkan secara rutin kemajuan proyek Serta menentukan teknik monitor dan penjadwalan. Hasil dari penelitian yang telah dilakukan memperlihatkan bahwa ada korelasi yang positif antara variabel-variabel penentu bebas peran Manajer Proyek dengan peningkatan kinerja waktu pada proyek bangunan gedung bertingkat di Jabotabek pada tahap pelaksanaan konstruksi."