Studi kelayakan pengusahaan sebuah pabrik besi spons di Batu Licin Kalimantan Selatan = Feasibility study of sponge iron plant in Batu Licin South Kalimantan / Nurhadi Wibowo

Nurhadi Wibowo; Rahmat Nurcahyo, supervisor; Djoko Sihono Gabriel, supervisor ([Publisher not identified] , 2013)

 Abstrak

ABSTRAK
Melimpahnya sumber daya mineral di Indonesia khususnya bijih besi serta adanya peraturan yang mendukung yaitu Undang-Undang No. 4 Tahun 2009 sehingga menghasilkan penelitian yang bertujuan untuk memperkirakan kelayakan suatu investasi dan besarnya biaya investasi pembangunan industri pengolahan pelet bijih besi di Indonesia, dengan mengevaluasi dari berbagai analisis kelayakan yang terdiri dari analisis pasar, analisis teknis, analisis organisasi dan analisis financial. Penelitian ini menganalisis investasi dan resiko dari keuangan dengan mempertimbangkan sumber pendanaan dan kesanggupan pembayaran mengangsur biaya pokok dan bunga pinjaman dari bank dengan suku bunga sebesar 14%. Perhitungan capital budgeting yang dilakukan menghasilkan NPV sebesar Rp 84.589.784.996 dan IRR 39,18% sehingga investasi pembangunan industri pengolahan pellet bijih besi dapat dikatakan layak karena nilai IRR berada di atas nilai MARR yaitu sebesar 20%. Analisa kepekaan menunjukkan bahwa faktor-faktor yang berpengaruh terhadap investasi adalah harga jual bahan baku dan penunjang serta harga produk jadi yang akan dijual ke pasar.

ABSTRACT
The abundance of mineral resources in Indonesia especially iron ore and the regulations supporting the Undang-Undang No. 4 in 2009 to produce research that aims to estimate the feasibility of an investment and the cost of investment development of iron ore pellets processing industry in Indonesia, to evaluate the feasibility of various analysis consists of market analysis, technical analysis, organizational analysis and financial analysis.This study analyzed the risk of financial investments and taking into account the financial resources and ability to repay the cost of principal and payment of interest on the loan from the bank with an interest rate of 14%. Capital budgeting calculations were done, resulting NPV Rp 84,589,784,996 and IRR 39.18% making investment development of iron ore pellets processing industry can be said to be feasible because the IRR is above the MARR value that is equal to 20%. Sensitivity analysis showed that the factors that affect the investment is the selling price of raw materials and finished product supporter and a price that will be sold to the market.

 Metadata

No. Panggil : T35206
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : [Place of publication not identified]: [Publisher not identified], 2013
Program Studi :
Bahasa : ind
Sumber Pengatalogan :
Tipe Konten : text
Tipe Media : unmediated
Tipe Carrier : volume
Deskripsi Fisik : xiv, 78 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
T35206 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20350320