:: UI - Tesis Membership :: Kembali

UI - Tesis Membership :: Kembali

Perancangan inspection plan dan pengukuran kerja aktvitas inspeksi packaging material pada industri susu bayi = Design of inspection plan and work measurement of packaging material inspection activity in baby milk industry

Andina Rahmasari; Teuku Yuri M. Zagloel, supervisor; Amalia Suzianti, supervisor; Erlinda Muslim, examiner; Boy Nurtjahyo Moch., examiner; Yadrifil, examiner (Fakultas Teknik Universitas Indonesia, 2014)

 Abstrak

[ABSTRAK
Salah satu aktivitas yang memegang peranan penting dalam menjamin kualitas
packaging material yang akan dipakai proses produksi adalah aktivitas inspeksi.
Dibutuhkan perancangan inspection plan yang komprehensif yaitu, sampling plan
yang mencakup penentuan sample size, analisis performa sampling plan tersebut
ke dalam bentuk Operating Characteristic Curve dan penentuan spesifikasi
attribute. Penentuan sample size dalam penelitian ini menggunakan MIL-STD
1916, karena menggunakan konsep ?zero accept one reject?. Output inspection
plan perlu dilengkapi dengan pengukuran kerja, karena aktivitas inspeksi tidak
terlepas dari sumber daya manusia yang melakukan di lapangan. Sehingga, kerja
inspektor juga mempengaruhi performa inspeksi. Dalam pengukuran kerja,
dihitung waktu standar yang dibutuhkan inspektor dalam melakukan inspeksi,
serta jumlah inspektor yang sesuai. Inspection plan dan pengukuran kerja saling
melengkapi satu sama lain dan perlu dilakukan keduanya secara berurutan ketika
merencanakan aktivitas inspeksi.

ABSTRACT
One of main activity that has important impact to make sure packaging material
quality that would be used in production process is inspection activity. There is
needed to design comprehensive inspection plan, include sampling plan that
consists of determination of sample size, analysis of sampling plan performance
in to Operating Characteristic Curve and determintation of attribute specification.
In this research, determination of sample size is using MIL-STD 1916, because it
is use ?zero accept one reject? concept. Output of inspection plan needs to be
completed by work measurement, because inspection activity can not be separated
from human resources, that work in workplace directly. So, inspector
performance also influence performance of inspection activity. In work
measurement, it would calculate the standard time that needed by inspector, and
calculate appropriate number of inspector. Inspection plan and work measurement
are complementary to each other and both needed to sequentially when planning
inspection activity.;One of main activity that has important impact to make sure packaging material
quality that would be used in production process is inspection activity. There is
needed to design comprehensive inspection plan, include sampling plan that
consists of determination of sample size, analysis of sampling plan performance
in to Operating Characteristic Curve and determintation of attribute specification.
In this research, determination of sample size is using MIL-STD 1916, because it
is use “zero accept one reject” concept. Output of inspection plan needs to be
completed by work measurement, because inspection activity can not be separated
from human resources, that work in workplace directly. So, inspector
performance also influence performance of inspection activity. In work
measurement, it would calculate the standard time that needed by inspector, and
calculate appropriate number of inspector. Inspection plan and work measurement
are complementary to each other and both needed to sequentially when planning
inspection activity., One of main activity that has important impact to make sure packaging material
quality that would be used in production process is inspection activity. There is
needed to design comprehensive inspection plan, include sampling plan that
consists of determination of sample size, analysis of sampling plan performance
in to Operating Characteristic Curve and determintation of attribute specification.
In this research, determination of sample size is using MIL-STD 1916, because it
is use “zero accept one reject” concept. Output of inspection plan needs to be
completed by work measurement, because inspection activity can not be separated
from human resources, that work in workplace directly. So, inspector
performance also influence performance of inspection activity. In work
measurement, it would calculate the standard time that needed by inspector, and
calculate appropriate number of inspector. Inspection plan and work measurement
are complementary to each other and both needed to sequentially when planning
inspection activity.]

 File Digital: 1

Shelf
 T41399-Andina Rahmasari.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : T41399
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2014
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xiv, 113 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
T41399 15-17-497559097 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20389293