:: UI - Tesis Membership :: Kembali

UI - Tesis Membership :: Kembali

Pengelolaan resiko penerapan metode konstruksi pembangunan jalan layang non tol untuk meningkatkan kinerja waktu di DKI Jakarta

Ni Made Kerthina Mela Octavia; Khrisna Mochtar, supervisor; Yusuf Latief, supervisor; Setyo Supriyadi Sipadi, examiner; Eddy Subiyanto, examiner; Ayomi Dita Rarasati, examiner (Fakultas Teknik Universitas Indonesia, 2014)

 Abstrak

[ABSTRAK
Pembangunan infrastruktur dalam bidang transportasi untuk menambah kapasitas jalan khususnya proyek Jalan Layang Non Tol merupakan salah satu alternatif yang diharapkan dapat menanggulangi masalah kemacetan lalu lintas di DKI Jakarta. Namun pada pelaksanaan proyek Jalan Layang Non Tol di DKI Jakarta mengalami keterlambatan dari rencana penyelesaian. Penelitian ini bertujuan untuk untuk mendapatkan resiko pada penerapan metode konstruksi yang
mempengaruhi kinerja waktu pembangunan Jalan Layang Non Tol yang dilihat dari sudut pandang pemilik proyek (owner) dan kontraktor. Resiko yang harus diperhatikan adalah resiko keterlambatan kedatangan alat pada tahapan erection box girder. Dengan melakukan menjadwalkan kedatangan alat dapat digunakan untuk mencegah munculnya resiko tersebut.;

ABSTRACT
Infrastructure development in the transportation sector to increase the road
capacity especially Jalan Layang Non Tol project is one alternative that expected
to solve the problem of traffic jam in Jakarta. However, the implementation of
Jalan Layang Non Tol project is delayed from the plan. This study aimed to
obtain the risk of the application of the construction method that affect the time
performance of Jalan Layang Non Tol development from the perspective of the
owner and contractor. The dominan risks that must be considered is delay in the
tools arrival on stade box girder erection. To prevent the dominan risk by doing
scheduled arrival of the tools.;Infrastructure development in the transportation sector to increase the road
capacity especially Jalan Layang Non Tol project is one alternative that expected
to solve the problem of traffic jam in Jakarta. However, the implementation of
Jalan Layang Non Tol project is delayed from the plan. This study aimed to
obtain the risk of the application of the construction method that affect the time
performance of Jalan Layang Non Tol development from the perspective of the
owner and contractor. The dominan risks that must be considered is delay in the
tools arrival on stade box girder erection. To prevent the dominan risk by doing
scheduled arrival of the tools.;Infrastructure development in the transportation sector to increase the road
capacity especially Jalan Layang Non Tol project is one alternative that expected
to solve the problem of traffic jam in Jakarta. However, the implementation of
Jalan Layang Non Tol project is delayed from the plan. This study aimed to
obtain the risk of the application of the construction method that affect the time
performance of Jalan Layang Non Tol development from the perspective of the
owner and contractor. The dominan risks that must be considered is delay in the
tools arrival on stade box girder erection. To prevent the dominan risk by doing
scheduled arrival of the tools.;Infrastructure development in the transportation sector to increase the road
capacity especially Jalan Layang Non Tol project is one alternative that expected
to solve the problem of traffic jam in Jakarta. However, the implementation of
Jalan Layang Non Tol project is delayed from the plan. This study aimed to
obtain the risk of the application of the construction method that affect the time
performance of Jalan Layang Non Tol development from the perspective of the
owner and contractor. The dominan risks that must be considered is delay in the
tools arrival on stade box girder erection. To prevent the dominan risk by doing
scheduled arrival of the tools., Infrastructure development in the transportation sector to increase the road
capacity especially Jalan Layang Non Tol project is one alternative that expected
to solve the problem of traffic jam in Jakarta. However, the implementation of
Jalan Layang Non Tol project is delayed from the plan. This study aimed to
obtain the risk of the application of the construction method that affect the time
performance of Jalan Layang Non Tol development from the perspective of the
owner and contractor. The dominan risks that must be considered is delay in the
tools arrival on stade box girder erection. To prevent the dominan risk by doing
scheduled arrival of the tools.]

 File Digital: 1

Shelf
 T42882-Ni Made Kerthina Mela Octavia.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : T42882
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Salemba: Fakultas Teknik Universitas Indonesia, 2014
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xviii, 185 pages : illustration ; 30 cm. + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
T42882 15-18-947554680 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20410487