Perencanaan penambahan kapasitas produksi untuk memenuhi proyeksi target produksi bahan bakar minyak BBM berdasarkan kapasitas unit proses studi kasus industri pengolahan minyak Indonesia = Planning of production capacity enhancement to meet projection of fuel production target based on process unit capacity case study of Indonesia Oil Refining Industry

([;Fakultas Teknik Universitas Indonesia;Fakultas Teknik Universitas Indonesia, Fakultas Teknik Universitas Indonesia], 2016)

 Abstrak

[Penelitian ini membahas mengenai perencanaan peningkatan kapasitas produksi
karena Capacity Availble saat ini tidak mampu memenuhi peningkatan Capacity
Requirement yang disebabkan oleh adanya proyeksi peningkatan target produksi
BBM. Perencanaan peningkatan kapasitas produksi dilakukan melalui tiga
alternatif, yakni alternatif subkontrak, alternatif penambahan mesin, dan alternatif
kombinasi penambahan mesin dan subkontrak. Pada tiga alternatif tersebut
dilakukan perhitungan kelayakan dan analisis sensitivitas. Hasil dari perhitungan
kelayakan dan analisis sensitivitas menunjukkan bahwa tiga alternatif peningkatan
kapasitas produksi tersebut layak untuk dilakukan, alternatif subkontrak
merupakan alternatif terbaik berdasarkan parameter NPV, dan alternatif
penambahan mesin merupakan alternatif terbaik berdasarkan parameter laba rugi.;This study discusses a planning of production capacity enhancement caused by an
increase in projection of fuel production target.This planning is done through
three alternatives of increasing production capacity, ie subcontracting, adding
machine, and combination of adding machine and subcontracting. The three
alternatives are conducted in feasibility calculation and sensitivity analysis.
Results of the feasibility calculation and sensitivity analysis shows the three
alternatives are feasible to do, subcontracting is the best alternative based on
NPV, and adding machine is the best alternative based on profit.;This study discusses a planning of production capacity enhancement caused by an
increase in projection of fuel production target.This planning is done through
three alternatives of increasing production capacity, ie subcontracting, adding
machine, and combination of adding machine and subcontracting. The three
alternatives are conducted in feasibility calculation and sensitivity analysis.
Results of the feasibility calculation and sensitivity analysis shows the three
alternatives are feasible to do, subcontracting is the best alternative based on
NPV, and adding machine is the best alternative based on profit., This study discusses a planning of production capacity enhancement caused by an
increase in projection of fuel production target.This planning is done through
three alternatives of increasing production capacity, ie subcontracting, adding
machine, and combination of adding machine and subcontracting. The three
alternatives are conducted in feasibility calculation and sensitivity analysis.
Results of the feasibility calculation and sensitivity analysis shows the three
alternatives are feasible to do, subcontracting is the best alternative based on
NPV, and adding machine is the best alternative based on profit.]

 File Digital: 1

Shelf
 S62043-Apriani Theresia.pdf :: Unduh

 Metadata

No. Panggil : S62043
Subjek :
Penerbitan : [Place of publication not identified]: [;Fakultas Teknik Universitas Indonesia;Fakultas Teknik Universitas Indonesia, Fakultas Teknik Universitas Indonesia], 2016
Program Studi :
Bahasa : ind
Sumber Pengatalogan :
Tipe Konten :
Tipe Media :
Tipe Carrier :
Deskripsi Fisik : xiii, 110 p. : ill. ; 28 cm.
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
S62043 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20421478