Identifikasi risiko fasilitas sementara pada tahap persiapan pengeboran oleh tunnel boring machine (TBM) dalam proyek mass rapid transit (MRT) Jakarta = Risk identification of temporary facilities in excavation preparation stage by tunnel boring machine (TBM) on mass rapid transit (MRT) Jakarta project
Choirunnisa Muthi`Ah;
Leni Sagita Riantini, supervisor; Ayomi Dita Rarasati, examiner; Rossy Armyn Machfudiyanto, examiner
(Fakultas Teknik Universitas Indonesia, 2017)
|
Pada konstruksi MRT Jakarta, pekerjaan tunnelling dilakukan dengan menggunakan alat Tunnel Boring Machine TBM . Salah satu tahap awal pada pelaksanaan pekerjaan terowongan menggunakan TBM adalah pembangunan fasilitas sementara TBM. Penelitian ini bertujuan untuk mengidentifikasi faktor-faktor risiko pada fasilitas sementara TBM yang berpengaruh terhadap kinerja waktu proyek MRT, dampak dan penyebabnya, serta tindakan yang dapat dilakukan terhadap faktor-faktor risiko tersebut. Penelitian dilakukan dengan mengumpulkan data melalui survey kuesioner dan wawancara. Kemudian, data tersebut diolah menggunakan uji-uji stastistik dan analisis kualitatif risiko. Hasil penelitian ini didapatkan lima faktor risiko fasilitas sementara TBM yang berpengaruh terhadap kinerja waktu proyek. Faktor risiko tertinggi pada fasilitas sementara TBM adalah ketidaksejajaran sumbu TBM dengan back anchor. Within Jakarta MRT construction, tunnelling work done by using a Tunnel Boring Machine TBM . One of the early stages of the implementation tunnelling work using a TBM is the construction of temporary facilities for TBM. This research has purposes to identify risk factors of temporary facilities for TBM that influence time performance of MRT project, its cause and effects, and also treatment or response that can do for that risk factors. The research was conducted by collecting data through a survey questionnaire and interview. Then, evaluated by statistics test and qualitative risk analyze. The result of this research is acquired five risk factors of temporary facilities for TBM that influence to time performance of MRT project. The highest risk of temporary facilities for TBM is misalignment of TBM axis with back anchor. |
S69306-Choirunnisa Muthi'ah.pdf :: Unduh
|
No. Panggil : | S69306 |
Entri utama-Nama orang : | |
Entri tambahan-Nama orang : | |
Subjek : | |
Penerbitan : | Depok: Fakultas Teknik Universitas Indonesia, 2017 |
Program Studi : |
Bahasa : | ind |
Sumber Pengatalogan : | LibUI ind rda |
Tipe Konten : | text |
Tipe Media : | unmediated ; computer |
Tipe Carrier : | volume ; online resource |
Deskripsi Fisik : | xx, 158 pages : illustration ; 28 cm + appendix |
Naskah Ringkas : | |
Lembaga Pemilik : | Universitas Indonesia |
Lokasi : | Perpustakaan UI, Lantai 3 |
No. Panggil | No. Barkod | Ketersediaan |
---|---|---|
S69306 | 14-19-939803016 | TERSEDIA |
Ulasan: |
Tidak ada ulasan pada koleksi ini: 20456871 |