Optimasi manajemen proyek menggunakan simulasi monte carlo dan critical path method "studi kasus proyek pemipaan high density polyethylene (HDPE) pada jaringan system air hydrant = Project management optimization with monte carlo simulation and critical path method case study high density polyethylene (HDPE) fire hydrant system project

Abdul Qodir Ramsah; Akhmad Hidayatno, supervisor; Zulkarnain, supervisor; Komarudin, examiner; Romadhani Ardi, examiner ([Publisher not identified] , 2018)

 Abstrak

ABSTRAK
Dalam pelaksanaannya proyek-proyek yang ada seringkali mengalami kegagalan. Menurut hasil survey kegagalan proyek standish group international, 2009 53 proyek mengalami kegagalan atau di bawah performa dan sebagian besar faktor penyebabnya adalah Organisasi dan praktik manajemen proyek yang kurang baik, Tujuan proyek yang tidak terdefinisi dengan baik, Perencanaan proyek yang tidak efektif, Personel yang kurang terampil, Permasalahan dengan supplier danTechnical Problem. Penelitian ini dianalisis dengan menggunakan metode CPM untuk aktivitas utama dan menggunakan simulasi monte carlo untuk memprediksi perkiraan perencaan sub-aktivitas pekerjaan pemipaan. Hasil dari simulasi monte carlo akan di compile dengan analisa CPM sehingga terbentuklah suatu pendjadwalan proyek yang di tampilkan dalam gannt chart scheduling. Peneliti juga menganalisa kebutuhan akan peralatan kerja dan tenaga kerja untuk suatu proyek dengan mengcompile kebutuhan tenaga kerja dan peralatan kerja pada masing masing aktivitas dengan gannt chart scheduling sehingga didapatkan pengorganisaian tenaga kerja dan peralatan kerja.

ABSTRACT
In the implementation of existing projects often fail or under perform. 53 of projects have failed and most of the contributing factors are poor organization and project management practices, poor definied or missing project objective, ineffective project planning, standish group international, 2009 . This study was analyzed by using the CPM method for the main activity and using monte carlo simulation to predict the approximate planning of the pipework sub activity. The results of monte carlo simulation will be compiled with CPM analysis so that a project scheduling is formed in the gannt chart scheduling. Researchers also analyzed the need for work equipment and labor a project by compiling the needs of labor and work equipment in each activity on the gannt chart scheduling so that it got the organizing of labor and work equipment.

 File Digital: 1

Shelf
 T49123-Abdul Qodir Ramsah .pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : T49123
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Depok: [Publisher not identified], 2018
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xv, 86 pages : illustration ; 28 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
T49123 15-18-474074029 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20467381