Analisis perbandingan penjadwalan proyek desain struktur ekor pesawat terbang buatan indonesia dengan critical path method cpm dan critical chain project management ccpm = Comparative analysis of empennage design indonesian aircraft project scheduling with critical path method cpm and critical chain project management ccpm

Arin Wulandari; M. Dachyar, supervisor; Rahmat Nurcahyo, examiner; Yadrifil, examiner; Laoh, Enrico, examiner (Fakultas Teknik Universitas Indonesia, 2018)

 Abstrak

ABSTRAK
Produksi pesawat terbang sendiri menjadi sangat penting untuk memfasilitasi banyaknya penumpang pesawat terbang di Indonesia. Indonesia memiliki sejumlah insinyur pesawat dalam membuat dan merancang komponen utama pesawat terbang yang kompleks. Namun, banyak insinyur pesawat Indonesia yang lebih memilih bekerja pada produsen pesawat dunia, termasuk para insinyur pesawat baru. Hal ini menyebabkan sumber daya manusia dalam mendesain pesawat di Indonesia menjadi terbatas. Desain pesawat terbang yang sangat kompleks dan jumlah sumber daya manusia yang terbatas membutuhkan manajemen proyek yang baik. Penelitian ini bertujuan untuk menganalisis perbandingan penjadwalan berdasarkan CPM dan CCPM untuk proses desain struktur ekor pesawat terbang berdasarkan sumber daya yang terbatas. Hasil analisis perbandingan menunjukan bahwa penjadwalan CPM dan CCPM memiliki ruang lingkup dan kualitas yang sama. Dalam constraint penjadwalan, CPM memiliki proses perhitungan yang lebih sederhana dibandingkan CCPM. Penjadwalan CCPM dapat lebih dapat meminimalisasi biaya, menggunakan sumber daya manusia lebih optimal, dan dapat lebih mengantisipasi risiko dibandingkan penjadwalan CPM.

ABSTRACT
AbstractThe production of the aircraft in Indonesia becomes very important to facilitate many passengers of airplanes in Indonesia. Indonesia has a number of aircraft engineers in making and designing the main components of a complex aircraft. However, many Indonesian aircraft engineers prefer to work on the world 39 s aircraft manufacturers, including new aircraft engineers. This causes the human resources in designing of aircraft in Indonesia to be limited. The design of a very complex aircraft and the limited number of human resources requires good project management. This study aims to analyze scheduling comparisons based on CPM and CCPM for the design process of tailplane structure based on limited resources. The result of comparison analysis shows that the scheduling of CPM and CCPM have the same scope and quality. In the scheduling constraint, CPM has a simpler calculation process than CCPM. CCPM scheduling can further minimize costs, use more optimal human resources, and be more risk anticipating than CPM scheduling.

 File Digital: 1

Shelf
 Arin Wulandari.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : S-Pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2018
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : unmediated ; computer (rdadontent)
Tipe Carrier : volume ; online resource
Deskripsi Fisik : xiv, 104 pages : illustration ; 29 cm + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
S-Pdf 14-18-866435845 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20472727