Perancangan instalasi pembangkit listrik tenaga surya dalam mega proyek jembatan Selat Sunda = Designing the installation of solar power plant in mega project Sunda Strait bridge

Janice Angelina Djaja; Farizal, supervisor; M. Dachyar, examiner; Rahmat Nurcahyo, examiner; Zulkarnain, examiner ([Publisher not identified] , 2018)

 Abstrak

ABSTRACT
Jembatan Selat Sunda JSS adalah jembatan yang dirancang untuk menghubungkan Pulau Jawa dan pulau Sumatra. Adapun proyek yang pernah diwacanakan akan dibangun pada masa pemerintahan Presiden Susilo Bambang Yudhoyono ini masih ditahan dan belum dilanjutkan kembali karena minimnya kemampuan pendanaan dan juga minat investor. Di sisi lain, secara geografis, lokasi JSS yang berada di Indonesia bagian barat memiliki potensi pengembangan energi surya yang sangat baik. Penelitian ini bertujuan untuk merancang pemanfaatan solar cell dalam pembangunan Jembatan Selat Sunda. Pembangkit Listrik Tenaga Surya PLTS akan dipasang di sepanjang JSS dan dikaji terlebih dahulu. Rancangan ini juga akan diintegrasikan dengan rancangan pada penelitian Berawi yang menambahkan fungsi pariwisata dalam pembangunan JSS. Hasil penelitian ini menunjukan instalasi PLTS dalam JSS layak untuk dilakukan. Adapun integrasi keseluruhan fungsi dalam JSS belum memiliki Net Present Value positif. Namun analisis sensitivitas yang dilakukan menunjukan rancangan secara keseluruhan dapat menjadi layak pada beberapa kondisi.

ABSTRACT
Sunda Strait Bridge is a bridge that is designed to connect Java Island and Sumatra Island. The project that aimed to be built in the era of Susilo Bambang Yudhoyono is currently stuck and can rsquo t be built because of the lack of money and investors rsquo interest. In the other hand, geographically, the location of Sunda Strait Bridge is in the eastern of Indonesia that has potency of development of solar energy. This research aim to design the utilization of solar cell in the construction of Sunda Strait Bridge. Solar Power Plant will be built along the 29 km bridge and will be reviewed. This research is also integrated with other research that was done by Berawi that designed another energy plant and tourism area in Sunda Strait Bridge. The result show that it is feasible to install solar power plant in Sunda Strait Bridge. However, the integration of all function has negative NPV. But after doing sensitivity analysis, it shows that the project will be feasible in some condition.

 File Digital: 1

Shelf
 Janice Angelina Djaja.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : S-Pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : [Place of publication not identified]: [Publisher not identified], 2018
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer recource
Tipe Carrier : online resource
Deskripsi Fisik : xiv, 76 pages : illustration ; appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, Lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
S-Pdf 14-20-988031092 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20472802