:: UI - Tugas Akhir :: Kembali

UI - Tugas Akhir :: Kembali

Dampak Pademi Covid-19 Terhadap Kontrak Konstruksi Proyek Jaringan Ketenagalistrikan PT PLN (Persero) = The Impact of Covid-19 Pandemic toward the Construction Contract of the Electrical Power Transmission Line Project of PT PLN (Persero)

Muhammad Zakir Machmaud, examiner; Muhammad Salman, supervisor; Sutrasno Kartohardjono, examiner; I Njoman Surjana D, supervisor (Fakultas Teknik Universitas Indonesia, 2021)

 Abstrak

Manajemen Proyek konstruksi yang dilaksanakan oleh Divisi Konstruksi meliputi
pembangunan Pembangkit, Transmisi dan Gardu Induk. Pada Divisi Konstruksi
Jawa Bagian Timur, Madura dan Bali bidang konstruksi jaringan memelakukan
fungsi pembinaan, pengawasan dan pengendalian kontrak konstruksi transmisi
dan gardu induk. Industri konstruksi di Indonesia tidak luput dari dampak
pandemi Covid-19 di Indonesia termasuk proyek jaringan ketenagalistrikan PT
PLN (Persero).
Pandemi Covid-19 menyebabkan timbulnya kebijakan dari pemerintah dalam hal
ini Gubernur, Bupati dan walikota untuk mencegah penyebaran covid-19 melalui
Pembatasan Sosial Berskala Besar (PSBB). Meskipun sektor konstruksi
merupakan tempat kerja/kantor yang masuk dalam kategori yang dikecualikan
namun PSBB memberikan dampak terhadap pembatasan interaksi kegiatan kerja
pada proyek konstruksi di PT PLN (Persero). Hal tersebut akan menyebabkan
terganggunya waktu penyelesaian pekerjaan karena sumber daya proyek (man,
material, machines) yang dibatasi. Pemberlakuan PSBB sebagai akibat dampak pandemi Covid-19 menyebabkan terganggunya penyelesaian pekerjaan Konstruksi Proyek Jaringan Ketenagalistrikan PT PLN (Persero) dan menyimpan potensi permasalahan dari sisi kontrak konstruksi yaitu berupa pengajuan klaim dari penyedia jasa berupa delay waktu pekerjaan, dan tambahan biaya. Mekanisme penanganan kontrak akibat dampak pandemi Covid-19 merujuk kepada ketentuan kontrak dan peraturan pengadaan barang dan jasa PT PLN (Persero). Penyelesaian klaim atas perubahan jadwal pelaksanaan pekerjaan dapat diberikan perpanjangan waktu pelaksanaan dengan melihat penyebab keterlambatan yaitu keterlambatan yang disebabkan oleh penyedia jasa dan keadaan yang terjadi diluar kehendak para pihak (keadaan kahar). Keterlambatan dari sisi pengguna jasa jika adanya larang perjalanan/pembatasan supervisi konstruksi sehubungan dengan peraturan internal PT PLN (Persero) dan Keterlambatan disebabkan keadaan kahar diberlakukan pada kondisi PSBB sebagai akibat dampak pandemi Covid-19. Pengajuan klaim tambahan biaya sehubungan dampak pandemi Covid-19 menurut pengadaan barang dan jasa PT PLN (Persero) diselesikan secara ketentuan kontrak melalui negosiasi musyawarah mufakat, namun jika mempertimbangkan ketentuan FIDIC atas dampak Covid-19 sebagai keadaan kahar maka hanya dapat diberikan kompensasi perpanjangan waktu tanpa kompensasi. Potensi sengketa kontrak dapat muncul apabila kedua bela pihak tidak sepakat terhadap tambahan biaya yang ditimbulkan sehingga sesuai kontrak diselesaikan melalui jalur arbitrase.

Construction Project Management carried out by the Construction Division includes the construction of Power Plants, Transmission and Substation. In the East Java, Madura and Bali Construction Division, the network construction sector carries out the functions of guidance, supervision and control of transmission and substation construction contracts. The construction industry in Indonesia has not escaped the impact of the Covid-19 pandemic in Indonesia, including the Electrical Power Transmission Line Project of PT PLN (Persero). The Covid-19 pandemic led to the emergence of policies from the government in this case the Governor, Regent and mayor to prevent the spread of Covid-19 through Large-Scale Social Restrictions (PSBB). Although the construction sector is a workplace / office that is included in the exempt category, PSBB has an impact on limiting the interaction of work activities on construction projects at PT PLN (Persero). This will disrupt the completion time of work because of limited project resources (man, material, machines).
The implementation of the PSBB as a result of the impact of the Covid-19 pandemic caused disruption in the completion the Electrical Power Transmission Line Project of PT PLN (Persero) and saved potential problems from the construction contract side, namely in the form of submitting claims from service providers in the form of work time delays and additional costs. The contract handling mechanism due to the impact of the Covid-19 pandemic refers to the contract provisions and regulations for the procurement of goods and services of PT PLN (Persero). Settlement of claims for changes to the schedule of work implementation can be given an extension of the implementation time by looking at the causes of delays, namely delays caused by service providers and conditions that occur outside the will of the parties (force majeure). Delays from the service user side if there is a travel ban / construction supervision restrictions in connection with the internal regulations of PT PLN (Persero) and the delay is due to force majeure imposed on PSBB conditions as a result of the impact of the Covid-19 pandemic. Submission of additional cost claims in connection with the impact of the Covid-19 pandemic according to the procurement of goods and services of PT PLN (Persero) is completed under contract terms through negotiation of consensus, but if you consider the FIDIC provisions for the impact of Covid-19 as a force majeure, compensation for extended time can only be given compensation. The potential for contract disputes can arise if the two parties do not agree on the additional costs incurred so that according to the contract it is resolved through arbitration.

 File Digital: 1

Shelf
 PR-Muhammad Zakir.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : PR-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Jakarta: Fakultas Teknik Universitas Indonesia, 2021
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xii, 46 pages : illustration + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI, lantai 3
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
PR-pdf 16-22-80461561 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20515079