Model percepatan penyelesaian proyek infrastruktur yang dibiayai pendanaan pinjaman luar negeri (Studi kasus: Bendungan X) = Acceleration model for completion of infrastructure projects using the foreign loan funding scheme (Case study: Dam x).

David Sanjaya Sutikno; Mohammed Ali Berawi, supervisor; Leni Sagita Riantini, examiner; Ayomi Dita Rarasati, examiner; Rossy Armyn Machfudiyanto, examiner (Fakultas Teknik Universitas Indonesia, 2021)

 Abstrak

Dalam proses pengerjaan proyek dapat terjadi hal-hal yang tidak diinginkan seperti keterlambatan pengerjaan proyek yang terjadi karena berbagai faktor seperti kondisi cuaca yang tidak mendukung, perubahan desain dan kesalahan perencanaan. Tidak terkecuali juga dalam pelaksanaan proyek dengan pinjaman luar negeri terdapat permasalahan terkait pencairan anggaran yang dapat mengakibatkan keterlambatan proyek. Penelitian ini menggunakan metode kuesioner kepada pemilik, konsultan pengawas, dan kontraktor yang berpengalaman dalam konstruksi bendungan sehingga didapatkan model percepatan penyelesaian proyek ini. Hasil penelitian ini didapatkan 4 faktor yang mempunyai tingkat kontribusi sangat tinggi dan 6 faktor tingkat kontribusi tinggi yang penyebab menjadi keterlambatan dalam kegiatan konstruksi infrastuktur bendungan X. Strategi percepatan yang digunakan adalah metode crashing dan hasilnya penyelesaian proyek lebih cepat 101 hari dari jadwal pelaksanaan semula dan kinerja pinjaman luar negeri masih behind schedule. Namun konsekuensi dari metode ini adalah terjadi kenaikan biaya konstruksi sebesar Rp 33.666.889.879 atau 2,83% dari biaya konstruksi awal dan kebutuhan biaya tersebut diambilkan dari dana kontijensi proyek.

In the process of working on the project, undesirable things can occur such as delays in project work that occur due to various factors such as unfavorable weather conditions, design changes and planning errors. There is also no exception in the implementation of projects with foreign loans, there are problems related to budget disbursement which can result in project delays. This study uses a questionnaire method to owners, supervisory consultants, and experienced contractors in dam construction to obtain a model for accelerating the completion of this project. The results of this study obtained 4 factors that have a very high level of contribution and 6 factors of a high level of contribution that cause delays in the construction of dam X. The acceleration strategy used is the crashing method and the result is that the project completion is 101 days faster than the original implementation schedule and performance foreign loans are behind schedule. However, the consequence of this method is an increase in construction costs of Rp. 33,666,889,879 or 2.83% of the initial construction cost and the required cost is taken from the project contingency fund..

 File Digital: 1

Shelf
 T-David Sanjaya Sutikno.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : T-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Depok: Fakultas Teknik Universitas Indonesia, 2021
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind rda
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xvii, 186 pages : illustration + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
T-pdf 15-22-20979802 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 20517243