:: UI - Tugas Akhir :: Kembali

UI - Tugas Akhir :: Kembali

Rekomendasi Perbaikan Manajemen Lingkup untuk Mengurangi Keterlambatan Proyek Studi Kasus PT Mitra Integrasi Informatika = Recommendations for Improvement of Scope Management to Reduce Project Delays Case Study PT Mitra Integrasi Informatika

Annisa Septiana Sani; Bob Hardian, supervisor; Teguh Rahardjo, supervisor; Heri Kurniawan, supervisor; Riri Satria, examiner (Fakultas Ilmu Komputer Universitas Indonesia, 2022)

 Abstrak

PT Mitra Integrasi Informatika (MII) merupakan perusahaan vendor yang memiliki jasa konsultasi dan solusi di bidang TIK. Saat ini sudah banyak proyek dari permintaan klien-klien yang diselesaikan oleh MII. Dalam melakukan bisnisnya, MII memiliki target penghasilan. Untuk mencapai target tersebut tentunya didukung oleh pengerjaan proyek yang sesuai dengan scope, timeline, dan budget. Namun, realita yang dimiliki saat ini, terdapat 68% dari total proyek mengalami keterlambatan delivery di tahun 2021 yang mempengaruhi pula pada pembengkakan biaya. Dari hasil analisis, didapatkan bahwa akar permasalahan terjadi pada area lingkup. Tujuan dari penelitian ini adalah untuk melakukan evaluasi dan memberikan usulan rekomendasi perbaikan proses kontrol terhadap lingkup dalam permintaan perubahan yang terjadi pada proyek di MII agar tidak mengalami keterlambatan delivery proyek yang berpengaruh pada reputasi perusahaan dan mencapai target penghasilan tahunan yang sudah ditetapkan. Penelitian ini bersifat kualitatif, menggunakan hasil wawancara dari narasumber sebagai landasan dalam melakukan analisis pada area manajemen lingkup proyek menggunakan praktik terbaik dari PMBOK.

PT Mitra Integrasi Informatika (MII) is a vendor company that has consulting services and solutions in the field of ICT. Currently, many projects from clients' requests have been completed by MII. In conducting its business, MII has an income target. To achieve this target, of course, it is supported by project work that is in accordance with the scope, timeline, and budget. However, the current reality is that 68% of the total projects experience delivery delays in 2021 which also affects cost overruns. From the results of the analysis, it was found that the root of the problem occurred in the scope area. The purpose of this study is to evaluate and provide recommendations for improvement of the control process on the scope of requests for changes that occur in projects at MII so as not to experience project delivery delays that affect the company's reputation and achieve the annual income target that has been set. This research is qualitative in nature, using the results of interviews from resource persons as a basis for analyzing the project scope management area using best practices from the PMBOK.

 File Digital: 1

Shelf
 TA-Annisa Septiana Sani.pdf :: Unduh

LOGIN required

 Metadata

No. Panggil : TA-pdf
Entri utama-Nama orang :
Entri tambahan-Nama orang :
Entri tambahan-Nama badan :
Subjek :
Penerbitan : Depok: Fakultas Ilmu Komputer Universitas Indonesia, 2022
Program Studi :
Bahasa : ind
Sumber Pengatalogan : LibUI ind
Tipe Konten : text
Tipe Media : computer
Tipe Carrier : online resource
Deskripsi Fisik : xiv, 192 pages + appendix
Naskah Ringkas :
Lembaga Pemilik : Universitas Indonesia
Lokasi : Perpustakaan UI
  • Ketersediaan
  • Ulasan
No. Panggil No. Barkod Ketersediaan
TA-pdf 16-23-62691824 TERSEDIA
Ulasan:
Tidak ada ulasan pada koleksi ini: 9999920521229