cover
Woro Liana Lestari
"Kinerja biaya suatu proyek dapat diukur dengan beberapa metode.Salah satunya, yaitu dengan menghitung varian biaya (cost variance), yaitu selisih antara biaya estimasi dan biaya aktual. Apabila varian biaya = 0, maka kinerja biaya proyek dianggap sesuai budget. Akan tetapi, apabila varian biaya bernilai negatif, maka proyek dianggap mengalami pembengkakan biaya (cost overrun). Cost overrun adalah permasalahan kronik yang hampir terjadi di setiap proyek. Pada proyek di industri otomotif, cost overrun ini sering terjaditerutama ketika perusahaan menangani proyek produk baru (new product project).
Penelitian ini mengambil contoh kasus cost overrun di PT. X pada 2 (dua) proyek perakitan mobil tipe SUV dan sedan, di mana pada kedua proyek tersebut terjadi pembengkakan biaya sebesar 184% (untuk proyek mobil sedan) dan 55.9% (untuk proyek mobil SUV). Pelaksanaan kedua proyek ini dilakukan secara partnering dengan sebuah perusahaan otomotif dari Jerman, yaitu Auto AG. Penelitian ini bertujuan untuk menganalisis faktor-faktor risiko penyebab cost overrun di PT. X pada saat perusahaan ini menjalankan proyek produk baru-nya secara partnering dengan Auto AG dan melihat bagaimana pengaruhnya terha-dap kinerja biaya proyek secara keseluruhan. Metode yang digunakan adalah metode kualitatif dengan studi literatur terlebih dahulu, di mana hasil literatur tersebut laludivalidasi oleh pakar dan beberapa responden melalui kuesioner. Analisis data yang digunakan pada penelitian ini, meliputi uji validitas dan reli-abilitas, uji kecukupan data dengan metode KMO, dan analisis risiko.
Hasil akhir-nya adalah faktor adanya perencanaan anggaran yang tidak tepat dan adanya peru-bahan yang terjadi di saat start-up tapi tidak terdokumentasi dengan baik menjadi dua faktor risiko tertinggi yang menyebabkan cost overrun pada new product project di PT. X.

Project cost performance can be measured within several methodes. One of them is by calculating the difference between the estimated cost and the actual cost or known as cost variance. If the cost variance = 0, the project cost performance is perfectly on-budget. But if the cost variance has negative value, the project is indicated of incurring cost overrun. Cost overrun is a chronic problem that happens in almost every project. In automotive industry, cost overrun happens several times when the company is having new product project.
This research takes sample from two cost overrun cases in PT. X when the company started assembling two kinds of new vehicle : SUV and passanger car. During their operation, the company had faced up cost overruns of more than 184% (for passenger car project) dan 55.9% (for SUV project). PT. X is running all of their new product projects in partnering with Auto AG, an automotive company from Germany. In this study, the risk factors causing cost overruns in new product project in PT. X, which was completed in partnering with Auto AG in Germany, will be further analyzed to find outwhichfactors that affect the overall project cost performance. This research uses qualitative method based on literature study.
The result from literature study is validatedby experts and some respondents by using questionnaire. The data collected from questionnaire is analyzed usingvalidity and reliability test, data adequacy testwith KMO method, and risk analysis. As the result, there are twodominant factors causing cost overrun in new product project in PT. X. Those two factors are the inappropriate usage of budget and changes during start up which are not well-documented.
"
Depok: Fakultas Teknik Universitas Indonesia, 2015
T44748
UI - Tesis Membership  Universitas Indonesia Library
cover
Heru Yandri
"Proyek Engineering, Procurement dan Construction (EPC) dilaksanakan dengan melibatkan banyak pihak dan memakai berbagai macam sumberdaya, dan juga menghadapi banyak masalah, masalah pengadaan menjadi penting karena resiko proyek EPC yang tinggi, persaingan antar perusahaan EPC dan porsi nilai pengadaan yang tinggi dalam pelaksanaan proyek.
Proses pengadaan sangat menentukan dalam keberhasilan kinerja biaya proyek karena rata-rata porsis pengadaan pada proyek EPC mencapai 70% dari nilai proyek. Tujuan dari penelitian ini adalah untuk menentukan strategi proses pengadaan yang efektif pada posisi critical dan leverage untuk meningkatkan biaya proyek EPC.
Penelitian untuk mengetahui strategi pengadaan dengan menggunakan teknik Delphi yang didapat dari wawancara dengan pakar project management dan metode AHP untuk analisa hasil kuesioner manajer proyek dan team inti proyek pada perusahaan PT X.

Engineering, procurement and construction project were involved with many participant and used to many kind of resources and too many problem, procurement problem to be important because EPC project high risk, EPC company competition and value of high procurement portion in project execution.
Procurement process very important to increase project cost performance because procurement portion average in EPC project almost seventy percent from project contract. Goal of this research is to prepare effectiveness of procurement process strategy in critical and leverage position to increase cost performance EPC project.
Research is to know procurement strategy with used Delphy method and AHP method to analyze result of questioner from PT. X
"
Depok: Fakultas Teknik Universitas Indonesia, 2008
T 24948
UI - Tesis Open  Universitas Indonesia Library
cover
Mutia Zahrina Putri
"Pada beberapa proyek di PT.X terdapat keluhan pembengkakan biaya akibat banyaknya pekerjaan rework. Hal ini diindikasikan karena kurangnya pengelolaan SDM. Tim proyek seharusnya direkrut dan dikelola agar memiliki kemampuan tertentu agar menghasilkan kinerja biaya yang baik salah satunya dengan meminimalisir rework. Namun acuan yang digunakan untuk mengembangkan kompetensi tersebut belum mempertimbangkan faktor- faktor risiko penyebab rework. Sebagai respon permasalahan, penelitian ini bertujuan untuk mengidentifikasi risiko yang dapat mempengaruhi tugas dan tanggung jawab tim proyek dalam pengendalian mutu agar tidak terjadi rework sehingga meningkatkan kinerja biaya, serta mengembangkan kompetensinya berdasarkan jobdesc baru dengan adanya aktifitas yang dibutuhkan untuk merespon risiko tersebut.
Metode penelitian yang digunakan adalah metode studi kasus dan metode survey. Sementara untuk mengetahui faktor risiko dominan menggunakan analisa risiko kualitatif. Penelitian ini menghasilkan sebuah tabel yang berisi elemen-elemen kompetensi beserta unjuk kerja terhadap 6 fungsi dalam organisasi proyek PT.X yang berperan dalam aktivitas respon risiko dominan yang telah diidentifikasi, serta modul pelatihan yang sesuai untuk mengisi gap kompetensi yang ada.

In some projects in PT.X cost overrun being big problem due to large number of rework. This is indicated due to lack of human resources management. Project teams should be recruited and managed to have a certain understanding and ability to be able to produce good performance by minimizing rework. As reponse, this study aims to identify risks that may affect the tasks and responsibilities of the project team in quality control in order to avoid rework so cost performance can be improve and then to develop its competence based on new jobdesc by the activities required to respond those risks.
The research method used is case study and survey. A case study conducted on PT.X as a building contractor. While the survey was conducted to determine the dominant risk factors using qualitative risk analysis. This study produces the elements of competence along with the performance of the 6 functions within the PT.X project organization that play a role in identified dominant risk response activities, as well as appropriate training modules to fill in the existing competency gap.
"
Depok: Fakultas Teknik Universitas Indonesia, 2018
T51427
UI - Tesis Membership  Universitas Indonesia Library
cover
Adib Karoma Yude
"PT X adalah perusahaan manufaktur yang memproduksi makanan dan minuman dengan aspek kesehatan. Sejak didirikan tahun 1979 hingga saat ini berusia 42 tahun, organisasi telah berkembang dan melakukan berbagai inovasi untuk bertahan dalam persaingan bisnis. Memasuki industri 4.0, PT X beradaptasi dengan perkembagan teknologi informasi. Perusahaan tengah dalam fase transformasi bisnis menjadi digital dengan melakukan pengembagan perangkat lunak yang bertujuan untuk mempermudah dan membuat proses bisnis menjadi lebih efektif dan efisien. Organisasi telah melakukan praktik manajemen proyek namun belum sepenuhnya diterapkan dengan baik. Hal ini dapat terlihat dari adanya 40% proyek yang dijalankan tidak dapat di-deliver dengan tepat waktu. Evaluasi perlu dilakukan untuk mengukur tingkat kematangan manajemen proyek yang sudah dijalankan sehingga organisasi dapat melakukan perbaikan. Dengan menggunakan Project Management Maturity Model (PMMM) diketahui bahwa tingkat kematangan manajemen proyek PT X berada pada tingkat pertama. Hal ini menunjukan bahwa pengetahuan organisasi mengenai manajemen proyek masih belum cukup baik.
Penelitian ini juga menghasilkan rekomendasi perbaikan yang dapat diterapkan organisasi yaitu mengadakan pelatihan khusus untuk setiap area manajemen proyek, membuat standar dokumentasi yang baik, mengadakan sesi pendalaman materi Project Management Body of Knowledge (PMBOK) dan mendorong project manager untuk berkomunikasi menggunakan istilah manajemen proyek yang tepat

.PT X is a food and beverage manufacturing company with a focus on health. Since its establishment in 1979, the organization has developed and implemented several innovations in order to remain competitive in the commercial sector. PT X has adapted to the advancement of information technology as it enters industry 4.0. The organization is in the process of digitalizing its business by building software to simplify and improve the effectiveness and efficiency of business operations. The organization has implemented project management practices, but they have not been properly applied. There are 40% of projects that cannot be delivered on schedule. Evaluation is required to determine the maturity level of project management that has been applied so that the organization could implement improvements. Using the Project Management Maturity Model (PMMM), it is determined that PT X's project management is at the first level of maturity. This indicates that the organization's understanding of project management is still insufficient. This research also includes recommendations for improvement that may be implemented by organization, such as providing particular training for each project management area, establishing appropriate documentation standards, organizing sessions to increase understanding of the Project Management Body of Knowledge (PMBOK) materials, and encouraging project managers to communicate using proper project management terms."
Depok: Fakultas Ilmu Komputer Universitas Indonesia, 2021
TA-pdf
UI - Tugas Akhir  Universitas Indonesia Library
cover
Agung Andika Putra
"Tingginya risiko dan ketidakpastian dalam tahap pelaksanaan manajemen material pada proyek EPC dapat menjadi salah satu penyebab penyimpangan biaya proyek. Salah satu strategi pengendalian untuk meminimalkan terjadinya penyimpangan biaya adalah mendeteksi sedini mungkin risiko risiko yang dapat terjadi pada tahap pelaksanaan manajemen material yang dituangkan kedalam prosedur pengendalian biaya material disetiap tahapan pelaksanaannya.
Penelitian ini bertujuan untuk menentukan alternatif preventive dan corrective action serta merekomendasikan pengembangan prosedur pengendalian biaya material berbasis risiko berdasarkan risiko utama penyebab penyimpangan. Untuk mengetahui besarnya frekwensi dan dampak risiko penyebab penyimpangan biaya material dilakukan penilaian secara kualitatif terhadap salah satu proyek yang mengalami penyimpangan biaya terbesar pada PT.Y, dengan melakukan wawancara pakar dan kuisioner kepada tim inti proyek yang mempunyai pengalaman dalam proyek EPC.
Analisa data diolah dengan analisa risiko kualitatif untuk memperoleh risiko utama penyebab penyimpangan, kemudian untuk dapat menentukan preventive dan corrective action serta rekomendasi pengembangan prosedur pengendalian biaya material berbasis risiko digunakan metode delphi.
Hasil analisa data ditemukan delapan penyebab utama terjadinya penyimpangan biaya material yaitu: Terjadi kesalahan dalam menentukan spesifikasi material karena kontrak yang kurang jelas; Terjadi kesalahan dalam menentukan spesifikasi material karena kurang lengkap atau akuratnya data informasi mengenai jenis-jenis material yang efektif; Terjadi revisi spesifikasi material akibat kesalahan pada design material (misdesign); Terjadi kesalahan dalam menentukan spesifikasi material karena kesalahan dalam memahami spesifikasi material yang tertera didalam kontrak; Terjadi pembelian ulang material karena kesalahan dalam penentuan spesifikasi material; Meningkatnya biaya pembelian material akibat tingginya harga material dipasaran; Meningkatnya biaya pembelian material akibat fluktuasi harga material dipasaran; Terjadi instalasi ulang material karena kesalahan design spesifikasi material.

The height of the risk and the uncertainty in the implementation stage of the material management in the EPC project could become one of the causes of project cost deviation. One of the controlling strategies to minimize the occurrence of the cost deviation is detecting the risks earlier that could happen in the implementation stage of the material management which is presented in the material cost controlling procedure in each implementation stage.
This research aimed to determine the alternative preventive and corrective action and also to recommend the development of the material cost controlling procedure based on the risk according to the main risk of the deviation cause. To recognize the frequency value and the impact of the risk as the cause of material cost deviation, it would be carried out by the assessment qualitatively towards one of the projects experienced in the biggest cost deviation to PT.Y, by interviewing experts and spreading questioner to the key person in the core project team that had experiences in the EPC project.
Data analysis would be processed by the qualitative risk analysis to find the main risk of the deviation cause, afterwards to be able in determining preventive and corrective action along with recommendation of the material cost controlling procedure development based on the risk used by the Delphi method.
Data analyzes resulted that eight main causes of material cost deviation were found, there are: Fault in determining material specification because of the unclear contract; Fault in determining the material specification because the data information about effective material kinds is not accurate and incomplete; revision of the material specification as the consequence of faulty in material design; the fault happened in determining the material specification because of the misunderstanding in defining the material specification that stated on contract; material repurchasing because of fault in determining of the material specification; the Increasing of material purchasing cost as consequence of material price increasing on market; the Increasing of material purchasing cost as consequence of material price fluctuation on market; material reinstallation happened because of the faulty design in material specification.
"
Depok: Fakultas Teknik Universitas Indonesia, 2008
T40652
UI - Tesis Open  Universitas Indonesia Library
cover
Hanifah Mardiana
"Dalam keterlibatan kompleks proyek konstruksi, kemampuan berkomunikasi diperlukan untuk berinteraksi karena apabila terdapat kesalahan, akan menyebabkan penyimpangan biaya, waktu, mutu. Pemahaman manajer proyek dalam manajemen komunikasi menjadi penting karena kekuatan manajer proyek dalam menyampaikan informasi kepada tim sangat berpengaruh. Tujuan penelitian ini adalah mencari faktor-faktor komunikasi dari pemahaman manajer proyek, aplikasinya, dan pengaruhnya terhadap mutu. Analisis yang dilakukan adalah mendata beberapa proyek di Jakarta dari PT. X dengan analisis statistic validitas dan reabilitas, non-parametrik, deskriptif, serta korelasi dan regresi. Dengan hasil ini dapat diketahui faktor-faktor komunikasi yang buruk yang mengakibatkan penurunan kinerja mutu dari implementasi manajer proyek.

In the complexity of construction project, ability of communicating is needed to decreases bad effects in cost, time, and quality. Comprehension of a project manager in project communication management being important because the power of project manager in informing is strongly influencing. The analysis for this research is taking data on projects in Jakarta from PT. X. Processing data is done by statistic analysis which is validity and realibility, non parametric, descriptive, correlation and regression analysis. With this product, will be found the communication factors that decreasing the quality performance from management communication project knowledge implementation of a project manager."
Depok: Fakultas Teknik Universitas Indonesia, 2008
S50550
UI - Skripsi Open  Universitas Indonesia Library
cover
Zul Effendi
"Pada tahap pelaksanaan konstruksi, perlu dilaksanakan pengendalian sehingga biaya aktual penyelesaian proyek tidak menyimpang dari rencana. Jika dalam pelaksanaan terjadi penyimpangan (cost variance) yang berakibat terjadi kelebihan biaya dari anggaran (cost overrun), perlu dilakukan identifikasi sumber penyebab penyimpangan tersebut. Salah satu variabel biaya proyek yang dapat dikendalikan adalah biaya peralatan. Kontribusi biaya peralatan mencapai 3-6% dari total biaya proyek konstruksi gedung bertingkat, jika terjadi penyimpangan akan berdampak menurunnya kinerja biaya proyek dengan menyumbangkan angka yang signifikan. Dalam proses pengendalian biaya, sumber penyebab penyimpangan ini dilakukan penelusuran untuk dilakukan tindakan koreksi yang diperlukan sehingga dapat memperbaiki kinerja biaya proyek. Dari penelitian ini dihasilkan 27 model tunggal tindakan koreksi dan 16 model berganda dari 31 kombinasi yang berasal dari 5 model tunggal terbaik yang signifikan dan diharapkan akan memperbaiki dan meningkatkan kinerja biaya proyek. Model tindakan koreksi yang paling berpengaruh adalah tindakan koreksi pada kelompok E. Pemeliharaan yaitu EI (harus memiliki manual operasi alat) dengan tingkat pengaruh 64,4% dan probabilitas keberhasilan 67,3% dan peningkatan tindakan koreksi yang dibutuhkan untuk mengembalikan kinerja kembali normal (kinerja realisasi sama dengan kinerja rencana) sebesar 5,57%.

To avoid cost variance of a project, it requires project control during the construction period. If a cost variance occurs which resulted in cost overruns, there is a need to indentify the cause of variance. One of the project variables that need to be controlled is equipment cost Equipment cost contributes about 3-6% of the total project cost in highrise building construction, Variance in equipment cost during cost can reduce project cost performance significantly. In the the cost control process, it is important to identify the causes of the variance in order to apply the most optimum corrective actions that can improve project This research has indentified 27 single regression models and 16 multiple regression models form 31 combinations based on the best 5 single models which significantly can improve project cost performance. The model that gives the highest impact are the corrective action in the maintenance category (E), which is the necessary to have equipment operation manual (El) which contribute 64,4% and probability of success of 67,3%, and corrective action required to rectify the performance to the normal level."
Depok: Fakultas Teknik Universitas Indonesia, 2003
T1726
UI - Tesis Membership  Universitas Indonesia Library
cover
Arie Wiryo Moeljadi
"Tesis ini membahas mengenai faktor risiko yang berpengaruh terhadap motivasi dan kinerja dalam penerapan sistem Reward dan Punishment pada proyek konstruksi. Peristiwa risiko yang dominan ditemukan dalam lima bagian, yaitu Falsafah Dasar, Persepsi Seluruh Karyawan, Manajemen Kinerja, Komunikasi dan Kompensasi. Masing-masing peristiwa yang dominan ini kemudian dicari dampak, penyebab, dan tindakan preventif. Tindakan preventif dimaksudkan agar pada proyek yang selanjutnya peristiwa ini tidak terjadi lagi.

The focus of this study is about Risk factors that influenced motivation and performance on the developement reward and punishment system on construction project. Dominant risk factors founded in five part, which is basic principle, employee perception, performance management, communication, compensation. After that we will look for the impact, the causes, and the preventive response for each of these factors. The responses means so that the risk will not happen on the next project."
Depok: Fakultas Teknik Universitas Indonesia, 2012
T31956
UI - Tesis Open  Universitas Indonesia Library
cover
Ferdi Firdausy
"Proyek EPC dan konstruksi umumnya memiliki tingkat kerumitan, dan ketidakpastian yang tinggi. Perubahan yang terjadi pada tahap engineering, konstruksi, sistem kontrol, dan sub-logistik akan berdampak pada kinerja biaya logistik dan pada akhirnya mempengaruhi margin proyek, lemahnya kontrol proyek, dan memiliki potensi risiko tinggi. Tujuan dari penelitian ini adalah untuk mengetahui variabel risiko yang mempengaruhi kinerja biaya logistik, memperoleh identifikasi risiko tinggi dari variabel engineering, construction, dan system control yang mempengaruhi kinerja biaya logistik serta menentukan tanggapan dan rekomendasi risiko kepada meningkatkan kinerja biaya logistik pada proyek EPC di lokasi terpencil. Data dikumpulkan dari studi literatur, wawancara dengan responden, dan pakar. Dari 51 jawaban responden, risiko yang teridentifikasi adalah 30 faktor yang ditinjau dari probabilitas dan dampaknya. Metodenya melalui analisis deskriptif, uji validitas & reliabilitas, dan analisis risiko kualitatif. Selanjutnya, tindak lanjut hasil risiko akan dilakukan melalui mitigasi proaktif dan reaktif. Penelitian ini menemukan 7% variabel ekstrim, dan 93% adalah kategori berisiko tinggi. Dengan demikian bahwa semua variabel mempengaruhi kinerja biaya logistik dimana lokasi proyek yang jauh merupakan salah satu faktor utama kinerja biaya logistik.

The EPC and construction projects generally have a high level of complexity, and uncertainty. The changes that have occurred in the engineering, construction, control systems, and sub-logistics stages will impact logistics cost performance and finally affect the project margins, weak of project control, and high risk. The purpose of this study is to determine the variable risk that affects the performance of logistics costs, to obtain high-risk identification of engineering, construction, and system control variables that affect the performance of logistics costs and to determine the risk responses and recommendations to improve logistics cost performance on EPC projects in remote locations. Data was collected from literature studies, interviews with respondents, and experts. By 51 respondents' answers, the risk was identified are 30 factors in terms of the probabilities and impact. The method through descriptive analysis, validity & reliability testing, and qualitative risk analysis. Further, the follow-up of risk results would carry out through proactive and reactive mitigation. This research found 7% of the variables were extreme, and 93% were high-risk categories. Thus it indicates that all variables affect the logistics costs performance where the remote project locations are one of the main factors in increasing the logistics costs."
Depok: Fakultas Teknik Universitas Indonesia, 2023
T-pdf
UI - Tesis Membership  Universitas Indonesia Library
cover
Renata Muchlis Budijanto
"In Order to increase the quality of project implementation much research will need to be carried out in Indonesia and abroad. In 1982 The Business Roundtable's team in the US found that opportunities to reduce project costs and schedules by using existing and new construction technology are lost because construction too often is relegated to operate as a production function separated from financial planning, scheduling, and engineering or architectural design. The Construction Industry Institute's (CII) Task Force defines this term as Constructability, which is the optimum integration of construction knowledge and experience in planning, engineering, procurement, and field operations to achieve overall project objectives.
As the customer, the owner gets what he insist on. As the leader of the project team, the owners play a vital role in using constructability to meet project objectives. Specific project documenting the constructability effort have shown that owners accrued an average reduction in total project cost of 4.3% and in project schedule of 7.5%_ These savings represented a 10-to-1 return on the owner's investment in constructability. Although significant saving can result, the opportunities available are often overlooked by owners.
This research was conducted to study the role of project owners for implementing constructability improvement during conceptual planning phase which leads to an improve project time performance of construction project in Jabotabek Area. A questionnaire survey was used as the method for collecting data. Statistical analysis was performed to analyze the data and to develop a regression model between the role of project owners for constructability improvement during conceptual planning phase and the performance of construction project's schedule.
The result of this study shows a positive linier correlation between the project owner's role for constructability improvement during conceptual planning phase and the project time performance. The main variables are assuring that key individual assigned to the project team each have appropriate experience with the project and clearly state the priority of the project objectives."
Depok: Fakultas Teknik Universitas Indonesia, 2001
T1141